Complete project overview

MahaRERA · Registration filing
Floors
18
Buildings
2
Parking
5 spaces
Land area
683 sq m
Sanctioned built-up
2,079 sq m

Timeline

RERA registeredMay 2018
Proposed completionDec 2023
TodayJul 2026
Construction progress
Basement (if any)0%
Podiums0%
Stilt floor0%
Water conservation…0%
Fire protection an…0%
Open Parking0%
OC-readiness97%
Excavation100%
Plinth100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
Water Supply100%
Sewerage (Chamber,…100%
Storm Water Drains100%
Electrical meter r…100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

DREAM ARIHANT INFRASTRUCTURE COMPANY

PartnershipPromoter type
Mumbai Suburban, MAHARASHTRABased in
2Projects
1City
2018–2025Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
2 projectson the public record across 2 projects
2,079 sq mbuilt-up filed
2,591 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Maharashtra Housing and Area Development Authority (MHADA)Housing Authority1 of 2 projects
Slum Rehabilitation AuthoritySlum Rehabilitation Authoritythis project1 of 2 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Kurla
Taluka
Kurla
District
Mumbai Suburban
Pincode
400077
Survey no.
CTS No 5913, F P No 83
North boundary
F P No 82
East boundary
F P No 80
South boundary
F P No 84
West boundary
Shrimad Ramchandra Lane
What’s nearby
Schools1 school within 500m · Library 1.5km away
HealthcareHospital 385m away · 11 clinics within 1km · Pharmacy within 500m
Lifestyle2 parks within 500m · Gym or sports centre 500m away · 25+ restaurants and cafes within 1km
ShoppingSupermarket 1.4km away · Bank 61m away
Getting around
Expressway 474 mPrimary road 1.1 km · Lal Bahadur Shastri MargRailway line 764 m · Central Railways Express LineRailway station 811m away (Ghatkopar)Bus stop within 1km
Water & environment
Water body 857 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Slum Rehabilitation Authority

Slum Rehabilitation Authority
Building Permit
Survey no. CTS No 5913, F P No 83

The promised possession date (30 Dec 2023) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Slum Rehabilitation Authority

Planning authority

Has approved 729 RERA projects3.6% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
554
On record
15,389 flats · 0 plots
Reach
4 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
Litigation5 cases on record, earliest 2016
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

1 complaint on MahaRERA’s register for this project 1 disposed.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.