Complete project overview

RERA Telangana · Registration filing
Units
63 units
Unit mix
1 × F00 S01, 1 × F00 S02, 1 × F00 S03, 1 × F00 S04, 1 × F01 S01, 1 × F01 S02, 1 × F01 S03, 1 × F01 S04, 1 × F01 S05, 1 × F01 S06, 1 × F01 S07, 1 × F01 S08, 1 × F01 S09, 1 × F01 S10, 1 × F01 S11, 1 × F01 S12, 1 × F01 S13, 1 × F01 S14, 1 × F02 S01, 1 × F02 S02, 1 × F02 S03, 1 × F02 S04, 1 × F02 S05, 1 × F02 S06, 1 × F02 S07, 1 × F02 S08, 1 × F02 S09, 1 × F02 S10, 1 × F02 S11, 1 × F02 S12, 1 × F02 S13, 1 × F02 S14, 1 × F02 S15, 1 × F03 S01, 1 × F03 S02, 1 × F03 S03, 1 × F03 S04, 1 × F03 S05, 1 × F03 S06, 1 × F03 S07, 1 × F03 S08, 1 × F03 S09, 1 × F03 S10, 1 × F03 S11, 1 × F03 S12, 1 × F03 S13, 1 × F03 S14, 1 × F03 S15, 1 × F04 S01, 1 × F04 S02, 1 × F04 S03, 1 × F04 S04, 1 × F04 S05, 1 × F04 S06, 1 × F04 S07, 1 × F04 S08, 1 × F04 S09, 1 × F04 S10, 1 × F04 S11, 1 × F04 S12, 1 × F04 S13, 1 × F04 S14, 1 × F04 S15
Saleable area
34–291 sq mper unit, as filed
Floors
5
Land area
2,060 sq m
Built-up area
5,935 sq m
Road widening
379 sq mland set aside for road widening

Timeline

RERA approvedJul 2021
Proposed completionJul 2025
TodayJul 2026
Construction progress

76.5% overall, as filed

Podiums0%
Stilt floor0%
Flat fit-out85%
OC-readiness85%
Internal finishes95%
Excavation100%
Basement & plinth100%
Superstructure100%
Stairs & lifts100%
External finishes100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

50 of 63 available
BuildingFloorTypeArea sq mAvailable
Easy Town Complex1F00 S012030 of 1
Easy Town Complex1F00 S022451 of 1
Easy Town Complex1F00 S032911 of 1
Easy Town Complex1F00 S04731 of 1
Easy Town Complex2F01 S01550 of 1
Easy Town Complex2F01 S02580 of 1
Easy Town Complex2F01 S03500 of 1
Easy Town Complex2F01 S04mortgaged370 of 1
Easy Town Complex2F01 S05mortgaged461 of 1
Easy Town Complex2F01 S06mortgaged451 of 1
Easy Town Complex2F01 S07mortgaged731 of 1
Easy Town Complex2F01 S08mortgaged721 of 1
Easy Town Complex2F01 S09340 of 1
Easy Town Complex2F01 S10341 of 1
Easy Town Complex2F01 S11781 of 1
Easy Town Complex2F01 S12540 of 1
Easy Town Complex2F01 S13540 of 1
Easy Town Complex2F01 S14440 of 1
Easy Town Complex3F02 S01551 of 1
Easy Town Complex3F02 S02581 of 1
Easy Town Complex3F02 S03mortgaged501 of 1
Easy Town Complex3F02 S04mortgaged371 of 1
Easy Town Complex3F02 S05mortgaged461 of 1
Easy Town Complex3F02 S06mortgaged451 of 1
Easy Town Complex3F02 S07mortgaged731 of 1
Easy Town Complex3F02 S08mortgaged721 of 1
Easy Town Complex3F02 S09341 of 1
Easy Town Complex3F02 S10341 of 1
Easy Town Complex3F02 S11mortgaged781 of 1
Easy Town Complex3F02 S12mortgaged541 of 1
Easy Town Complex3F02 S13mortgaged541 of 1
Easy Town Complex3F02 S14mortgaged441 of 1
Easy Town Complex3F02 S15651 of 1
Easy Town Complex4F03 S01551 of 1
Easy Town Complex4F03 S02580 of 1
Easy Town Complex4F03 S03501 of 1
Easy Town Complex4F03 S04371 of 1
Easy Town Complex4F03 S05461 of 1
Easy Town Complex4F03 S06451 of 1
Easy Town Complex4F03 S07731 of 1
Easy Town Complex4F03 S08721 of 1
Easy Town Complex4F03 S09340 of 1
Easy Town Complex4F03 S10341 of 1
Easy Town Complex4F03 S11781 of 1
Easy Town Complex4F03 S12541 of 1
Easy Town Complex4F03 S13540 of 1
Easy Town Complex4F03 S14441 of 1
Easy Town Complex4F03 S15911 of 1
Easy Town Complex5F04 S01551 of 1
Easy Town Complex5F04 S02581 of 1
Easy Town Complex5F04 S03501 of 1
Easy Town Complex5F04 S04371 of 1
Easy Town Complex5F04 S05461 of 1
Easy Town Complex5F04 S06451 of 1
Easy Town Complex5F04 S07731 of 1
Easy Town Complex5F04 S08721 of 1
Easy Town Complex5F04 S09340 of 1
Easy Town Complex5F04 S10341 of 1
Easy Town Complex5F04 S11781 of 1
Easy Town Complex5F04 S12541 of 1
Easy Town Complex5F04 S13541 of 1
Easy Town Complex5F04 S14441 of 1
Easy Town Complex5F04 S15911 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

Tripura Constructions

PartnershipPromoter type
Ranga Reddy, TelanganaBased in
6Projects
4Cities
2019–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
1,032 homeson the public record across 6 projects
2,44,041 sq mbuilt-up filed
1,61,063 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Hyderabad Metropolitan Development Authority (HMDA)Urban Development Authority5 of 6 projects
Greater Hyderabad Municipal Corporation (GHMC)Municipal / Corporationthis project1 of 6 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
Medchal
Mandal
Medchal
District
Medchal-Malkajgiri
Pincode
500096
North boundary
P S Venkateswarulu Apartment
East boundary
Part of Survey Number 116
South boundary
House pf Akula Narasaiah
West boundary
NH Road from Nagpur to Hyderabad
What’s nearby
Schools2 schools within 1km · College or university 1.2km away
HealthcareHospital 761m away · 1 clinic within 1km · Pharmacy within 500m
Lifestyle1 park within 500m · Gym or sports centre 1.2km away · 12+ restaurants and cafes within 1km
ShoppingSupermarket 535m away · Mall 1.6km away · Bank 522m away
Getting around
Expressway 2.4 km · Golkonda RoadPrimary road 1.2 km · Road No. 2Railway line 4.7 kmMetro station 1.5km away (Jubilee Hills Checkpost)Bus stop within 1km
Declared external development
Water supply30%
Fire safety25%
Electricity25%
Rainwater20%
Green Strip/TOT LO…20%
Roads0%
Sewerage (Chamber,…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Greater Hyderabad Municipal Corporation (GHMC)

Municipal / Corporation
Building Permit
Survey no. 116

The promised possession date (5 Jul 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

GHMC

Municipal Corporation · Hyderabad city core

Has approved 3,102 RERA projectsabout 1 in 4 in Telangana.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,994
On record
2,20,211 flats · 3,387 plots
Reach
65 mandals
Since
2016

More apartment-heavy than Telangana overall — 99% apartments here vs 66% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.