HORIZONMarkets
01

Complete project overview

RERA Telangana · Registration filing
Units
515 units
Unit mix
375 × 3BHK, 140 × 2BHK
Saleable area
118–188 sq mper unit, as filed
Floors
10
Buildings
6
Land area
21,750 sq m
Built-up area
86,583 sq m

Timeline

RERA approvedJun 2020
Proposed completionJul 2026
TodayJul 2026
Construction progress

65% overall, as filed

Podiums0%
Flat fit-out0%
Internal finishes10%
OC-readiness40%
Excavation100%
Basement & plinth100%
Stilt floor100%
Superstructure100%
Stairs & lifts100%
External finishes100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

354 of 515 available
BuildingFloorTypeArea sq mAvailable
BLUE TRUMPET BLOCK C13BHKmortgaged1884 of 4
BLUE TRUMPET BLOCK C12BHKmortgaged1182 of 2
BLUE TRUMPET BLOCK C13BHKmortgaged1382 of 2
BLUE TRUMPET BLOCK C23BHKmortgaged1884 of 4
BLUE TRUMPET BLOCK C22BHKmortgaged1182 of 2
BLUE TRUMPET BLOCK C23BHKmortgaged1382 of 2
BLUE TRUMPET BLOCK C33BHK1882 of 4
BLUE TRUMPET BLOCK C32BHK1182 of 2
BLUE TRUMPET BLOCK C33BHK1380 of 2
BLUE TRUMPET BLOCK C43BHK1880 of 4
BLUE TRUMPET BLOCK C42BHK1182 of 2
BLUE TRUMPET BLOCK C43BHK1381 of 2
BLUE TRUMPET BLOCK C53BHK1883 of 4
BLUE TRUMPET BLOCK C52BHK1182 of 2
BLUE TRUMPET BLOCK C53BHK1380 of 2
BLUE TRUMPET BLOCK C63BHK1883 of 4
BLUE TRUMPET BLOCK C62BHK1181 of 2
BLUE TRUMPET BLOCK C63BHK1381 of 2
BLUE TRUMPET BLOCK C73BHK1881 of 4
BLUE TRUMPET BLOCK C72BHK1180 of 2
BLUE TRUMPET BLOCK C73BHK1381 of 2
BLUE TRUMPET BLOCK C83BHK1883 of 4
BLUE TRUMPET BLOCK C82BHK1181 of 2
BLUE TRUMPET BLOCK C83BHK1380 of 2
BLUE TRUMPET BLOCK C93BHK1882 of 4
BLUE TRUMPET BLOCK C92BHK1181 of 2
BLUE TRUMPET BLOCK C93BHK1381 of 1
BLUE TRUMPET BLOCK C93BHK1741 of 1
BLUE TRUMPET BLOCK C103BHK1883 of 4
BLUE TRUMPET BLOCK C102BHK1182 of 2
BLUE TRUMPET BLOCK C103BHK1380 of 2
GOLDEN RAIN BLOCK B13BHKmortgaged1884 of 4
GOLDEN RAIN BLOCK B12BHKmortgaged1182 of 2
GOLDEN RAIN BLOCK B23BHKmortgaged1884 of 4
GOLDEN RAIN BLOCK B22BHKmortgaged1182 of 2
GOLDEN RAIN BLOCK B33BHK1881 of 2
GOLDEN RAIN BLOCK B32BHK1180 of 1
GOLDEN RAIN BLOCK B43BHK1882 of 4
GOLDEN RAIN BLOCK B42BHK1182 of 2
GOLDEN RAIN BLOCK B53BHK1884 of 4
GOLDEN RAIN BLOCK B52BHK1182 of 2
GOLDEN RAIN BLOCK B63BHK1884 of 4
GOLDEN RAIN BLOCK B62BHK1182 of 2
GOLDEN RAIN BLOCK B73BHK1883 of 4
GOLDEN RAIN BLOCK B72BHK1181 of 2
GOLDEN RAIN BLOCK B83BHK1883 of 4
GOLDEN RAIN BLOCK B82BHK1181 of 2
GOLDEN RAIN BLOCK B93BHK1883 of 4
GOLDEN RAIN BLOCK B92BHK1182 of 2
GOLDEN RAIN BLOCK B103BHK1883 of 4
GOLDEN RAIN BLOCK B102BHK1181 of 2
RED MAPLE BLOCK D13BHKmortgaged1883 of 3
RED MAPLE BLOCK D12BHKmortgaged1187 of 7
RED MAPLE BLOCK D23BHKmortgaged1884 of 4
RED MAPLE BLOCK D22BHKmortgaged1186 of 6
RED MAPLE BLOCK D33BHK1882 of 5
RED MAPLE BLOCK D32BHK1182 of 6
RED MAPLE BLOCK D43BHK1884 of 4
RED MAPLE BLOCK D42BHK1184 of 6
RED MAPLE BLOCK D53BHK1883 of 4
RED MAPLE BLOCK D52BHK1184 of 6
RED MAPLE BLOCK D63BHK1884 of 4
RED MAPLE BLOCK D62BHK1185 of 6
RED MAPLE BLOCK D73BHK1883 of 4
RED MAPLE BLOCK D72BHK1184 of 6
RED MAPLE BLOCK D83BHK1884 of 4
RED MAPLE BLOCK D82BHK1185 of 6
RED MAPLE BLOCK D93BHK1884 of 4
RED MAPLE BLOCK D92BHK1184 of 6
RED MAPLE BLOCK D103BHK1884 of 4
RED MAPLE BLOCK D102BHK1184 of 6
RITU-SILVER FIR BLOCK E13BHKmortgaged1546 of 6
RITU-SILVER FIR BLOCK E13BHKmortgaged1882 of 2
RITU-SILVER FIR BLOCK E23BHKmortgaged1545 of 5
RITU-SILVER FIR BLOCK E23BHK1541 of 1
RITU-SILVER FIR BLOCK E23BHK1881 of 1
RITU-SILVER FIR BLOCK E23BHKmortgaged1881 of 1
RITU-SILVER FIR BLOCK E33BHK1540 of 6
RITU-SILVER FIR BLOCK E33BHK1881 of 2
RITU-SILVER FIR BLOCK E43BHK1544 of 6
RITU-SILVER FIR BLOCK E43BHK1882 of 2
RITU-SILVER FIR BLOCK E53BHK1543 of 6
RITU-SILVER FIR BLOCK E53BHK1881 of 2
RITU-SILVER FIR BLOCK E63BHK1542 of 6
RITU-SILVER FIR BLOCK E63BHK1882 of 2
RITU-SILVER FIR BLOCK E73BHK1541 of 4
RITU-SILVER FIR BLOCK E73BHK1881 of 2
RITU-SILVER FIR BLOCK E83BHK1544 of 7
RITU-SILVER FIR BLOCK E83BHK1880 of 1
RITU-SILVER FIR BLOCK E93BHK1544 of 6
RITU-SILVER FIR BLOCK E93BHK1882 of 2
RITU-SILVER FIR BLOCK E103BHK1546 of 6
RITU-SILVER FIR BLOCK E103BHK1882 of 2
WHITE OAK BLOCK F13BHKmortgaged1802 of 2
WHITE OAK BLOCK F13BHKmortgaged1544 of 4
WHITE OAK BLOCK F13BHKmortgaged1882 of 2
WHITE OAK BLOCK F23BHKmortgaged1802 of 2
WHITE OAK BLOCK F23BHKmortgaged1544 of 4
WHITE OAK BLOCK F23BHKmortgaged1882 of 2
WHITE OAK BLOCK F33BHK1802 of 2
WHITE OAK BLOCK F33BHK1541 of 4
WHITE OAK BLOCK F33BHK1882 of 2
WHITE OAK BLOCK F43BHK1801 of 2
WHITE OAK BLOCK F43BHK1540 of 3
WHITE OAK BLOCK F43BHK1881 of 2
WHITE OAK BLOCK F43BHK1541 of 1
WHITE OAK BLOCK F53BHK1801 of 2
WHITE OAK BLOCK F53BHK1544 of 4
WHITE OAK BLOCK F53BHK1882 of 2
WHITE OAK BLOCK F63BHK1801 of 2
WHITE OAK BLOCK F63BHK1540 of 4
WHITE OAK BLOCK F63BHK1881 of 2
WHITE OAK BLOCK F73BHK1801 of 2
WHITE OAK BLOCK F73BHK1542 of 4
WHITE OAK BLOCK F73BHK1880 of 2
WHITE OAK BLOCK F83BHK1802 of 2
WHITE OAK BLOCK F83BHK1542 of 4
WHITE OAK BLOCK F83BHK1882 of 2
WHITE OAK BLOCK F93BHK1802 of 2
WHITE OAK BLOCK F93BHK1543 of 4
WHITE OAK BLOCK F93BHK1881 of 2
WHITE OAK BLOCK F103BHK1801 of 2
WHITE OAK BLOCK F103BHK1543 of 4
WHITE OAK BLOCK F103BHK1882 of 2
YELLOW FLAME BLOCK A13BHKmortgaged1384 of 4
YELLOW FLAME BLOCK A13BHKmortgaged1883 of 3
YELLOW FLAME BLOCK A12BHKmortgaged1184 of 4
YELLOW FLAME BLOCK A13BHKmortgaged1181 of 1
YELLOW FLAME BLOCK A23BHKmortgaged1884 of 4
YELLOW FLAME BLOCK A22BHKmortgaged1184 of 4
YELLOW FLAME BLOCK A23BHKmortgaged1384 of 4
YELLOW FLAME BLOCK A33BHK1882 of 3
YELLOW FLAME BLOCK A33BHKmortgaged1881 of 1
YELLOW FLAME BLOCK A32BHK1180 of 4
YELLOW FLAME BLOCK A33BHK1381 of 4
YELLOW FLAME BLOCK A43BHK1884 of 4
YELLOW FLAME BLOCK A42BHK1181 of 4
YELLOW FLAME BLOCK A43BHK1383 of 4
YELLOW FLAME BLOCK A53BHK1882 of 4
YELLOW FLAME BLOCK A52BHK1182 of 4
YELLOW FLAME BLOCK A53BHK1381 of 4
YELLOW FLAME BLOCK A63BHK1884 of 4
YELLOW FLAME BLOCK A62BHK1180 of 1
YELLOW FLAME BLOCK A63BHK1382 of 4
YELLOW FLAME BLOCK A62BHK1181 of 3
YELLOW FLAME BLOCK A73BHK1882 of 4
YELLOW FLAME BLOCK A72BHK1181 of 4
YELLOW FLAME BLOCK A73BHK1383 of 4
YELLOW FLAME BLOCK A83BHK1882 of 4
YELLOW FLAME BLOCK A82BHK1180 of 4
YELLOW FLAME BLOCK A83BHK1384 of 4
YELLOW FLAME BLOCK A93BHK1882 of 4
YELLOW FLAME BLOCK A92BHK1183 of 4
YELLOW FLAME BLOCK A93BHK1384 of 4
YELLOW FLAME BLOCK A102BHK1183 of 4
YELLOW FLAME BLOCK A103BHK1881 of 2
YELLOW FLAME BLOCK A103BHK1381 of 5

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

Tripura Constructions

PartnershipPromoter type
Ranga Reddy, TelanganaBased in
6Projects
4Cities
2019–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
1,032 homeson the public record across 6 projects
2,44,041 sq mbuilt-up filed
1,61,063 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Hyderabad Metropolitan Development Authority (HMDA)Urban Development Authoritythis project5 of 6 projects
Greater Hyderabad Municipal Corporation (GHMC)Municipal / Corporation1 of 6 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
TELLAPUR
Village
TELAPUR
Mandal
RC PURAM
District
Sangareddy
Pincode
502032
North boundary
VACANT LAND
East boundary
VACANT LAND
South boundary
ROAD WIDTH 18 MTR
West boundary
VACANT LAND
What’s nearby
SchoolsNearest school 1.2km away · College or university 1.9km away · Kindergarten within 500m
HealthcareNearest hospital 2.7km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 4.8 kmPrimary road 3.2 km · Nallagandla FlyoverRailway line 1.2 kmRailway station 1.3km away (Telapur)Limited bus connectivity nearby
Water & environment
Water body 377 m
distances only — not a flood assessment
Government land classification

No residential (House Sites) class on record. The state classes this village’s land as Dry land, Wet Land double crop. If it’s sold as residential plots, verify the layout’s conversion / approval.

Telangana Registration & Stamps
Declared external development
Sewerage (Chamber,…100%
Water supply80%
Rainwater80%
Fire safety80%
Street lighting70%
Rainwater70%
Electricity70%
Solid waste60%
Community Building…50%
Sewage50%
Roads0%
Green Strip/TOT LO…0%
Renewable energy0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Hyderabad Metropolitan Development Authority (HMDA)

Urban Development Authority
Building Permit no. 020648/SKP/R1/U6/HMDSurvey no. SURVEY NO 368/AA2 368/EE1/2 368/EE2 368/U 368/U3 368/U4
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 020648/SKP/R1/U6/HMD on the approving authority’s portal to confirm the sanction.

The approving body, at scale

HMDA

Urban Development Authority · Hyderabad metropolitan periphery

Has approved 3,643 RERA projectsabout 1 in 3 in Telangana.

an apartments market72% apartments · 28% plotted layouts. Apartments like yours are this body's core business.

Builders
2,462
On record
3,98,695 flats · 1,96,015 plots
Reach
71 mandals
Since
2016

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.