Complete project overview

K-RERA · Registration filing
Units
52 units
Mix
22 × 3BHK · 20 × 2BHK · 10 × 4BHK
Booked
52 of 52 filed sold/bookedas declared in the RERA filing
Buildings
1
Land area
3,085 sq m
Floor area
12,559 sq m
Description
ELEVE MAISON

Timeline

Project startedOct 2019
RERA registeredApr 2021
Proposed completionApr 2024
TodayJul 2026
Construction progress

81% overall, as filed

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Slabs of Super Structure46%
Sanitary Fittings70%
Electrical Fittings95%
Excavation100%
Basement(s) and Plinth100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Fire Fighting Fittings and Equipment100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Per-activity completion % from the promoter's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

0 of 52 available
TypeArea sq mAvailable
4BHK2220 of 1
4BHK2170 of 1
4BHK2180 of 8
2BHK960 of 20
3BHK1200 of 22

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system.

02

Builder’s track record

K-RERA · Promoter registration

GALAXY BUILDERS

PartnershipPromoter type
Kozhikode, KeralaBased in
Yes — the promoter declared prior project experienceDeclared prior experience
5Projects
1City
2021–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
283 homes · 181 plotson the public record across 5 projects
75,459 sq mbuilt-up filed
15,697 sq mland declared
₹8.10 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Kozhikode Municipal CorporationMunicipal Corporationthis project3 of 5 projects
AshtaTown & Country Planning (DTCP)1 of 5 projects
Olavanna Grama PanchayatGrama Panchayat1 of 5 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

K-RERA · Registration filing
Street
PHED ROAD
Village
KACHERY
Taluk
Kozhikode
District
Kozhikode
Pincode
673006
Survey no.
81/3, 78/2
Patta no.
1974
What’s nearby
SchoolsNearest school 1.9km away · College or university 1.9km away · Library 722m away
HealthcareHospital 37m away · Clinic within 2km
LifestyleNo parks within 2km · 9 restaurants and cafes within 1km
ShoppingSupermarket 493m away · ATM within 500m
Getting around
Expressway 1.3 km · Kannur-Calicut-Valanchery Highway NH 66Primary road 117 m · Kuttiyadi RoadRailway line 1.9 kmRailway station 2.1km away (Elattur)2 bus stops within 500m
Water & environment
Water body 419 m · temple pond,Sree Vellikalakulangara KshethramkulamRiver 1.2 kmCanal 1.5 km
distances only — not a flood assessment
Land, title & encumbrance
Land ownershipBuilt on land that includes third-party owners — a landowner (joint-development) arrangement is declared; confirm the title and your share
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
04

Planning authority

K-RERA · Approved building plan

Kozhikode Municipal Corporation

Municipal Corporation
approved 7 Aug 2019 · 6 yrs ago
Building Permit no. TP/ 3NEW-BA(224147) / 2019Survey no. 81/3, 78/2

The promised possession date (20 Apr 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan TP/ 3NEW-BA(224147) / 2019 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

Kozhikode Municipal Corporation

Municipal corporation / municipality

Has approved 57 RERA projects3.7% of Kerala.

an apartments market96% apartments · 4% plotted layouts. Apartments like yours are this body's core business.

Builders
36
On record
3,822 flats · 80 plots
Since
2021

More apartment-heavy than Kerala overall — 96% apartments here vs 81% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — K-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — K-RERA does not publish a complaints register. This read cannot speak to them either way.