HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
14
Buildings
6
Parking
76 spaces
Land area
12,100 sq m
Sanctioned built-up
11,831 sq m
Recreational open space
1,151 sq m

Timeline

RERA registeredJun 2025
Proposed completionDec 2028
TodayJul 2026
Construction progress
Excavation0%
Basement (if any)0%
Podiums0%
Plinth0%
Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Street Lighting0%
Community Building…0%
Treatment And Disp…0%
Solid Waste Manage…0%
Water conservation…0%
Energy managemcnt0%
Fire protection an…0%
Electrical meter r…0%
Aggregate area of …0%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Omkara Developers

PartnershipPromoter type
Pune, MAHARASHTRABased in
1Projects
1City
2025–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Nere
Taluka
Mulshi
District
Pune
Pincode
411033
Survey no.
Servey No 33/1(P) 33/2 of Nere Village, Tal- Mulshi, Pune
North boundary
ODR
East boundary
34
South boundary
32
West boundary
40
What’s nearby
SchoolsNearest school 1.1km away · 10 educational institutions within 1km · College or university 570m away
HealthcareHospital 895m away · 1 clinic within 1km · Pharmacy within 500m
LifestylePark 768m away · Gym or sports centre 1.0km away · 12+ restaurants and cafes within 1km
ShoppingSupermarket 978m away · Mall 937m away · Convenience store within 500m
Getting around
Expressway 2.4 km · Katraj - Dehu Road BypassPrimary road 543 m · Akurdi Chikhali RoadRailway line 810 m · Mumbai–Pune RailwayRailway station 902m away (Akurdi Railway Station)Bus stop within 1km
Water & environment
River 996 m · Pavana RiverWater body 1.2 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Pmc

Building Permit
Survey no. Servey No 33/1(P) 33/2 of Nere Village, Tal- Mulshi, Pune
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Pmc

Planning authority

Has approved 114 RERA projects0.6% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
91
On record
1,806 flats · 0 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.