HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
18
Buildings
2
Parking
210 spaces
Land area
1,740 sq m
Sanctioned built-up
6,995 sq m

Timeline

RERA registeredJul 2024
Proposed completionJun 2029
TodayJul 2026
Construction progress
External finishes20%
Water Supply30%
OC-readiness45%
Flat fit-out50%
Internal finishes65%
Electrical meter r…65%
Stilt floor90%
Excavation100%
Basement (if any)100%
Podiums100%
Plinth100%
Superstructure100%
Stairs & lifts100%
Internal Roads & F…100%
Sewerage (Chamber,…100%
Storm Water Drains100%
Landscaping & Tree…100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

PRABHAKAR KUNTE CO OPERATIVE HOUSING SOCIETY LIMITED

SocietyPromoter type
Mumbai Suburban, MAHARASHTRABased in
1Projects
1City
2024–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Oshiwara
Taluka
Andheri
District
Mumbai Suburban
Pincode
400102
Survey no.
CTS NO 1(pt), S.NO. 41
North boundary
PETROL PUMP
East boundary
OPEN SPACE
South boundary
OPEN SPACE RESERVED FOR GARDEN
West boundary
27 45 SQ MTR WIDE ROAD
What’s nearby
Schools4 schools within 1km · 5 educational institutions within 1km · Library 983m away
HealthcareHospital 332m away · 6 clinics within 1km · Pharmacy within 500m
LifestylePark 1.6km away · Gym or sports centre 596m away · 54+ restaurants and cafes within 1km
ShoppingSupermarket 500m away · Mall 610m away · Convenience store within 1km
Getting around
Expressway 2.2 kmPrimary road 253 m · Behrambaug RoadRailway line 1.7 km · Central Railway (Harbour Line)Metro station 27m away (Oshiwara)Bus stop within 1km
04

Planning authority

MahaRERA · Approved building plan

Municipal Corporation of Greater Mumbai

Municipal Corporation
Building Permit
Survey no. CTS NO 1(pt), S.NO. 41
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation of Greater Mumbai

Municipal corporation

Has approved 2,862 RERA projectsabout 1 in 7 in Maharashtra, more than any other body in the state.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
2,166
On record
34,498 flats · 0 plots
Reach
9 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.