Complete project overview
MahaRERA · Registration filing- Floors
- 37
- Buildings
- 2
- Land area
- 4,550 sq m
- Sanctioned built-up
- 2,078 sq m
- Recreational open space
- 460 sq m
Timeline
RERA registeredAug 2017
Proposed completionJun 2021
TodayJul 2026
Construction progressPer-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
Stilt floor0%
Aggregate area of …10%
LIGHTNING ARRESTER90%
Internal Roads & F…98%
Water Supply98%
Sewerage (Chamber,…98%
Storm Water Drains98%
Landscaping & Tree…98%
Street Lighting98%
Community Building…98%
Treatment And Disp…98%
Solid Waste Manage…98%
Water conservation…98%
Energy managemcnt98%
Fire protection an…98%
Electrical meter r…98%
Excavation100%
Basement (if any)100%
Podiums100%
Plinth100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
02
Builder’s track record
MahaRERA · Promoter registrationBHATIA BUILDERS AND DEVELOPERS PVT LTDC
CompanyPromoter type
Mumbai Suburban, MAHARASHTRABased in
3Projects
1City
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
32 homeson the public record across 3 projects
6,433 sq mbuilt-up filed
11,223 sq mland declared
These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.
Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
03
Location
MahaRERA · Registration filing- Village
- Borivali
- Taluka
- Borivali
- District
- Mumbai Suburban
- Pincode
- 400066
- Survey no.
- CTS 79, 79/1-30
- North boundary
- 120 FT ROAD
- East boundary
- 60 FT ROAD
- South boundary
- HYUNDAI SERVICE CENTRE
- West boundary
- 120 FT ROAD
What’s nearby
Schools1 school within 1km · Library 1.4km away
HealthcareHospital 99m away · 6 clinics within 1km · Doctor's clinic within 1km
LifestylePark 1.1km away · Gym or sports centre 504m away · Swimming pool within 2km
ShoppingSupermarket 669m away · Mall 928m away · Convenience store within 1km
Getting around
Expressway 291 mPrimary road 742 mRailway line 386 m · FCIMetro station 410m away (Devipada)Bus stop within 500m
Water & environment
River 1.2 km · Dahisar RiverWater body 1.4 km · Veer Savarkar Udyan Pond
distances only — not a flood assessmentLegal & regulatory recordFrom MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
LitigationNone declared to MahaRERA
Appeals1 appeal before the tribunal
2 complaints on MahaRERA’s register for this project — 2 disposed.
A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.
What this record cannot tell you
- Build quality — no filing records how well it was actually built.
- Private disputes — only complaints escalated to the authority appear here.
- What it will be worth — the record is the past; it does not price the future.