HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
15
Buildings
4
Parking
1 spaces
Land area
13,169 sq m
Sanctioned built-up
24,113 sq m
Recreational open space
1,463 sq m

Timeline

RERA registeredAug 2019
Proposed completionDec 2025
TodayJul 2026
Construction progress
Aggregate area of …0%
External finishes1%
Flat fit-out2%
OC-readiness5%
Fire protection an…25%
Stairs & lifts50%
Internal finishes72%
Electrical meter r…80%
Landscaping & Tree…92%
Sewerage (Chamber,…98%
Excavation100%
Basement (if any)100%
Podiums100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal Roads & F…100%
Water Supply100%
Storm Water Drains100%
Street Lighting100%
Community Building…100%
Treatment And Disp…100%
Solid Waste Manage…100%
Water conservation…100%
Energy managemcnt100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

VENTURESPRO PROJECTS LLP

PartnershipPromoter type
Pune, MAHARASHTRABased in
4Projects
1City
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
173 homeson the public record across 4 projects
39,394 sq mbuilt-up filed
27,688 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Ghorpadi
Taluka
Haveli
District
Pune
Pincode
411001
Survey no.
Sr No 464/B, 465, 466, 467
North boundary
Sr No 53-1
East boundary
Moujje Hadapsar
South boundary
Sr No 53-4
West boundary
BT Kawade Road
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 149m away · Clinic within 2km · Pharmacy within 1km
LifestylePark 1.5km away · Gym or sports centre 1.6km away
ShoppingSupermarket 86m away · Mall 1.5km away · Bank 608m away
Getting around
Expressway 1.3 km · Solapur RoadPrimary road 2.9 km · Moledina RoadRailway line 353 m · Pune - Miraj Railway LineRailway station 1.7km away (Ghorpuri)Limited bus connectivity nearby
Water & environment
Canal 354 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Pune Municipal Corporation

Municipal Corporation
Building Permit
Survey no. Sr No 464/B, 465, 466, 467

The promised possession date (30 Dec 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Pune Municipal Corporation

Municipal corporation

Has approved 1,863 RERA projectsabout 1 in 11 in Maharashtra.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,351
On record
9,749 flats · 439 plots
Reach
3 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
Litigation1 case on record, earliest 2013
EncumbranceDeclared financial encumbrance on the project
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

1 complaint on MahaRERA’s register for this project 0 disposed, 1 still open.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.