HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
5
Buildings
2
Parking
31 spaces
Land area
425 sq m
Sanctioned built-up
638 sq m

Timeline

RERA registeredJun 2023
Proposed completionDec 2026
TodayJul 2026
Construction progress
Basement (if any)0%
Podiums0%
Stilt floor0%
Flat fit-out0%
OC-readiness0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Street Lighting0%
Water conservation…0%
Electrical meter r…0%
Open Parking0%
External finishes60%
Internal finishes75%
Stairs & lifts80%
Excavation100%
Plinth100%
Superstructure100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

EVERNEST PERFECTINFRA LLP

PartnershipPromoter type
Pune, MAHARASHTRABased in
1Projects
1City
2023–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Bhosari
Taluka
Haveli
District
Pune
Pincode
411039
Survey no.
SURVEY NO 679/2A/2A
North boundary
BY PROPERTY OF MR SANJAY GUND
East boundary
BY 6 METER WIDE ROAD
South boundary
BY PROPERTY OF MR DHIRAJ LANDGE
West boundary
BY PROPERTY OF MR BALU LANDGE
What’s nearby
SchoolsNearest school 1.3km away · College or university 1.3km away
HealthcareHospital 142m away · 1 clinic within 1km
LifestylePark 1.4km away · Gym or sports centre 1.5km away · Swimming pool within 2km
ShoppingSupermarket 1.9km away
Getting around
Expressway 441 m · Pune Nashik RoadPrimary road 109 m · Nigdi Bhosari RoadRailway line 2.7 km · Mumbai–Pune RailwayRailway station 2.6km away (Kasarwadi)Bus stop within 1km
Water & environment
Water body 576 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Pune Municipal Corporation

Municipal Corporation
Building Permit
Survey no. SURVEY NO 679/2A/2A
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Pune Municipal Corporation

Municipal corporation

Has approved 1,863 RERA projectsabout 1 in 11 in Maharashtra.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,351
On record
9,749 flats · 439 plots
Reach
3 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

1 complaint on MahaRERA’s register for this project 1 disposed.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.