Registration lapsed

This project’s MahaRERA registration has lapsed— it expired and was not renewed. A lapsed project may be stalled, finished-but-not-updated, or abandoned; the record stops here and RERA’s ongoing protections may no longer apply. Confirm the current status directly with MahaRERA before you rely on anything below.

01

Complete project overview

MahaRERA · Registration filing
Floors
8
Buildings
2
Parking
12 spaces
Land area
690 sq m
Sanctioned built-up
1,676 sq m

Timeline

RERA registeredDec 2021
Proposed completionDec 2025
TodayJul 2026
02

Builder’s track record

MahaRERA · Promoter registration

Arvind Raychand Mutha

IndividualPromoter type
Aurangabad, MAHARASHTRABased in
1Projects
1City
2021–2025Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Aurangabad (M Corp.)
Taluka
Aurangabad
District
Aurangabad
Pincode
431003
Survey no.
Plot no 2 CTS no 16029/34
North boundary
Plot no 3
East boundary
Plot no 8 and 9
South boundary
Plot no 1
West boundary
24 mts Road
What’s nearby
Schools2 schools within 1km · College or university 1.1km away
HealthcareHospital 235m away · 2 clinics within 1km
LifestylePark 844m away · Gym or sports centre 1.8km away · 11+ restaurants and cafes within 1km
ShoppingSupermarket 817m away · Mall 2.0km away · Bank 373m away
Getting around
Expressway 674 m · Kranti Chowk FlyoverPrimary road 660 m · Kranti ChowkRailway line 1.3 kmRailway station 2.1km away (Chhatrapati Sambhajinagar)Bus stop within 1km
Water & environment
River 1.9 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Amc

Building Permit
Survey no. Plot no 2 CTS no 16029/34

The promised possession date (16 Dec 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

The planning authority

The body that sanctioned this project. It has approved 4,607 RERA projects across 33 districts about 1 in 4 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.