HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
14
Buildings
4
Parking
62 spaces
Land area
7,677 sq m
Sanctioned built-up
11,211 sq m
Recreational open space
2,164 sq m

Timeline

RERA registeredFeb 2023
Proposed completionDec 2025
TodayJul 2026
Construction progress
Basement (if any)0%
Podiums0%
Stilt floor0%
External finishes93%
OC-readiness93%
Excavation100%
Plinth100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
Internal Roads & F…100%
Water Supply100%
Sewerage (Chamber,…100%
Storm Water Drains100%
Landscaping & Tree…100%
Street Lighting100%
Community Building…100%
Treatment And Disp…100%
Solid Waste Manage…100%
Water conservation…100%
Energy managemcnt100%
Fire protection an…100%
Electrical meter r…100%
Aggregate area of …100%
Open Parking100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

RAMA SYNERGY SPACES

PartnershipPromoter type
Pune, MAHARASHTRABased in
16Projects
2Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
2,060 homeson the public record across 16 projects
1,75,346 sq mbuilt-up filed
1,00,537 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Bhoirwadi
Taluka
Mulshi
District
Pune
Pincode
411057
Survey no.
S. No. 41/A/5, 41/A/14, 41/A/15, 41/A/16
North boundary
Phase II
East boundary
Adj S No 21
South boundary
15 M wide internal Road
West boundary
F building and open space
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 1.5km away · Clinic within 2km
LifestyleNo parks within 2km · Gym or sports centre 556m away · 3 restaurants and cafes within 1km
ShoppingNo supermarket within 2km · Bank 838m away
Getting around
Primary road 689 m · TCS CircleMetro station 1.1km away (Megapolis Circle)Bus stop within 1km
Water & environment
Water body 626 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Pimpri Chinchwad Municipal Corporation

Municipal Corporation
Building Permit
Survey no. S. No. 41/A/5, 41/A/14, 41/A/15, 41/A/16

The promised possession date (31 Dec 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Pimpri Chinchwad Municipal Corporation

Municipal corporation

Has approved 1,391 RERA projectsabout 1 in 14 in Maharashtra.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,080
On record
9,009 flats · 249 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
EncumbranceDeclared financial encumbrance on the project
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.