01

Complete project overview

MahaRERA · Registration filing
Units
12 units
Floors
4
Buildings
2
Parking
14 spaces
Land area
532 sq m
Sanctioned built-up
471 sq m

Timeline

RERA registeredApr 2021
Proposed completionJul 2024
TodaySep 2026
Construction progress
Podiums0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Community Building…0%
Treatment And Disp…0%
Solid Waste Manage…0%
Water conservation…0%
Energy managemcnt0%
Electrical meter r…0%
Open Parking0%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

KSQUARE REALTY PRIVATE LIMITED

CompanyPromoter type
Mumbai Suburban, MAHARASHTRABased in
2Projects
1City
2021–2024Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
56 homeson the public record across 2 projects
1,959 sq mbuilt-up filed
2,197 sq mland declared

These are sums of what the builder has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from KSQUARE REALTY PRIVATE LIMITED— the full portfolio →

03

Location

MahaRERA · Registration filing
Village
Virathan Kh.
Taluka
Palghar
District
Palghar
Pincode
401102
Survey no.
56/2
North boundary
VEDHI-VIRATHANKHURD ROAD
East boundary
LAND OFMADHUKAR TUKARAM PATIL
South boundary
LAND OF MADHUKAR TUKARAM PATIL
West boundary
LAND OF CHANDRAPRABHA CHITRANJANSHAH
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 1.1km away
LifestylePark 1.0km away
ShoppingNo supermarket within 2km
Getting around
Primary road 741 mRailway line 1.2 km · Mumbai - Delhi RailwayRailway station 1.3km away (Saphale)Limited bus connectivity nearby
Water & environment
Water body 190 mRiver 4.8 km · Taki
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra IGR — Annual Statement of Rates

In Maharashtra it’s called the ready reckoner rate.

₹30,937per sq yd
₹37,000per sq m
Which rate
residential building or flat
Matched to
The rate published for the village of “Virathan Kh.”.
In force
2026-2027 schedule

What this number is — and isn’t

  • The minimum value Maharashtra’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
  • Not a market price. Sales normally register above it, and how far above varies by place and by project.
  • Its fit depends on the grain the state publishes at. This one is matched at the level of village, and says so above. How Horizon decides what to show.
05

Planning authority

MahaRERA · Approved building plan

District Commissioner Of Palghar

Building Permit
Survey no. 56/2

The promised possession date (31 Jul 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

The planning authority

The body that approved this project. It has approved 4,607 RERA projects across 33 districts about 1 in 4 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

07

Other projects nearby

The register · within 25 km

881 residential projects still under way within 25 km. Step out ring by ring:

13 projects within 1 km — showing the nearest 6.

Virathan Kh.Residential / Group Housing

STAR VIRATHAN CITY

STAR BUILDERS & DEVELOPERS

Jan 2025registered
Dec 2031target completion
Government Guidance Rate₹30,937/sq ydScale274 flatsAuthorityMahaRERA
MakaneResidential / Group Housing

STAR SIGNATURE CITY - STAR OPAL

STAR BUILDERS & DEVELOPERS

Jul 2024registered
Jun 2028target completion
Government Guidance Rate₹32,275/sq ydScale35 flatsAuthorityMahaRERA
MakaneResidential / Group Housing

ANGEL HOMES

SHREENATHJI DEVELOPERS

Apr 2026registered
Dec 2029target completion
Government Guidance Rate₹32,275/sq ydScale29 flatsAuthorityMahaRERA
MakaneResidential / Group Housing

NINE STAR CROWN BLDG NO. 4 SAPPHIRE

NINE HOMEMAKERS

Mar 2026registered
Dec 2031target completion
Government Guidance Rate₹32,275/sq ydScale62 flatsAuthorityMahaRERA
KapaseResidential / Group Housing

SIDDHIVINAYAK APARTMENT

ANANTA SB DEVELOPERS

Jan 2025registered
Dec 2026target completion
Government Guidance Rate₹27,258/sq ydScale47 flatsAuthorityMahaRERA
MakaneResidential / Group Housing

NINE STAR CROWN BLDG NO. 6 DIAMOND

NINE HOMEMAKERS

Jun 2026registered
Dec 2031target completion
Government Guidance Rate₹32,275/sq ydScale90 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. This project’s coordinate is approximate, so distances are rough.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.