HORIZON
Share

GALAXY DELIGHT

T1/OL/008/2021 · K-RERA · https://gethorizon.in/projects/galaxy-delight-thirumala-thiruvananthapuram-17ravlkb

01

Complete project overview

K-RERA · Registration filing
Units
10 units
Mix
9 × 3BHK · 1 × 2BHK
Buildings
1
Land area
536 sq m
Floor area
1,432 sq m
Description
GALAXY DELIGHT

Timeline

Project startedSep 2020
RERA registeredMar 2021
Proposed completionSep 2022
TodaySep 2026
Construction progress

87% overall, as filed

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation100%
Basement(s) and Plinth100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Fire Fighting Fittings and Equipment100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Per-activity completion % from the builder's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the builder registered — not a per-flat listing. Look yours up.

10 of 10 available
TypeArea sq mAvailable
2BHK541 of 1
3BHK1043 of 3
3BHK1043 of 3
3BHK893 of 3

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the builder declared — not a live booking system.

02

Builder’s track record

K-RERA · Builder registration

USHUS KUMAR SADASIVAN

Thiruvananthapuram, KeralaBased in
Yes — the promoter declared prior project experienceDeclared prior experience
1Projects
1Cities
2021–2022Active
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

K-RERA · Registration filing
Street
KESARI LANE
Village
THIRUMALA
Taluk
THIRUVANANTHAPRUAM
District
Thiruvananthapuram
Pincode
695012
Survey no.
BL/121/64
Patta no.
34375
What’s nearby
Schools3 schools within 1km · 5 educational institutions within 1km · Library 1.0km away
HealthcareHospital 478m away · 3 clinics within 1km · Pharmacy within 1km
LifestylePark 965m away · Gym or sports centre 984m away
ShoppingSupermarket 427m away · Mall 235m away · Convenience store within 1km
Getting around
Primary road 3.6 kmRailway line 3.2 kmRailway station 4.9km away (Thiruvananthapuram Central)10 bus stops within 500m
Water & environment
Water body 325 m · Kushakode Temple kulamRiver 1.2 km · Karamana River
distances only — not a flood assessment
04

Government Guidance Rate

Kerala Registration Department — fair value

In Kerala it’s called the fair value.

₹3,311per sq yd
₹3,960per sq m
Which rate
Residential Plot with Corp./Mun./Panch. road access
Matched to
The rate published for the village of “Thirumala”.

What this number is — and isn’t

  • The minimum value Kerala’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
  • Not a market price. Sales normally register above it, and how far above varies by place and by project.
  • Its fit depends on the grain the state publishes at. This one is matched at the level of village, and says so above. How Horizon decides what to show.
05

Planning authority

K-RERA · Approved building plan

Corporation

Local body (LSGI)
approved 26 May 2020 · 6 yrs ago
Building Permit no. E3/BA/8763/2020Survey no. BL/121/64

The promised possession date (19 Sep 2022) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

Verify it yourself — look up plan E3/BA/8763/2020 on the approving authority’s portal to confirm the approval.

The approving body, at scale

Corporation

Local body

Has approved 6 RERA projects0.4% of Kerala.

a mixed market67% apartments · 33% plotted layouts.

Builders
5
On record
263 flats · 19 plots
Reach
3 districts
Since
2021

More layout-heavy than Kerala overall — 33% plots here vs 19% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by K-RERA

07

Other projects nearby

The register · within 25 km

166 residential projects still under way within 25 km. Step out ring by ring:

1 project within 1 km — showing the nearest 1.

THIRUMALAResidential (Apartment)

Leela Madhavam Legacy by SI Property

SI Property Kerala Private Limited

Sep 2022registered
Dec 2027target completion
Government Guidance Rate₹3,311/sq ydScale39 flatsAuthorityK-RERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. This project’s coordinate is approximate, so distances are rough.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — K-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — K-RERA does not publish a complaints register. This read cannot speak to them either way.