Complete project overview

MahaRERA · Registration filing
Project name
Galaxy Heights
Floors
7
Land area
1,693 sq m
Sanctioned built-up
7,381 sq m

Timeline

RERA registeredJun 2023
Proposed completionDec 2027
TodaySep 2026
Construction progress
Podiums0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Sewerage (Chamber,…0%
Stilt floor5%
Water Supply5%
Basement (if any)36%
Plinth36%
Excavation69%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

Sky Point Builders

PartnershipPromoter type
Amravati, MAHARASHTRABased in
1Projects
1City
2023–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Amravati (M Corp.)
Taluka
Amravati
District
Amravati
Pincode
444602
Survey no.
Plot No 5/2, Nazul Sheet No 13 At Mauje Camp
North boundary
Prop Of Mr Mohd Abdul
East boundary
24 mtr Wide Public Road
South boundary
Prop of Mr Zoeb
West boundary
Prop of Mohd Akram Sayeed
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 3.2km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Primary road 458 mNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
River 1.4 km · Pedhi
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra IGR — Annual Statement of Rates

In Maharashtra it’s called the ready reckoner rate.

₹21,154per sq yd
₹25,300per sq m
Which rate
residential flat (built)
Matched to
The middle rate across the 19 divisions of “Amravati (M Corp.)” — the city's middle, not this project's own division.
In force
2026-2027 schedule
Spread
₹16,689₹27,960 per sq yd across the places it was taken over

What this number is — and isn’t

  • The minimum value Maharashtra’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
  • Not a market price. Sales normally register above it, and how far above varies by place and by project.
  • Its fit depends on the grain the state publishes at. This one is matched at the level of city, and says so above. How Horizon decides what to show.
05

Planning authority

MahaRERA · Approved building plan

Amravati Municipal Corporation

Municipal Corporation
Building Permit
Survey no. Plot No 5/2, Nazul Sheet No 13 At Mauje Camp
The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Amravati Municipal Corporation

Municipal corporation

Has approved 57 RERA projects0.3% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
56
On record
467 flats · 0 plots
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

73 residential projects still under way within 25 km. The nearest 6:

10.3 km awayOthers

Vasudeo Apartment

Saurabh Raju Ingole · Amravati

Mar 2022registered
Mar 2027target completion
Government Guidance Rate₹21,154/sq ydScale32 flatsAuthorityMahaRERA
10.3 km awayMixed

Shree Gajanan Residency

Saurabh Construction and Developers · Amravati

Sep 2025registered
Dec 2028target completion
Government Guidance Rate₹21,154/sq ydScale30 flatsAuthorityMahaRERA
10.7 km awayOthers

VARMA HEIGHTS

DILIP NANDKISHOR VARMA · Amravati

Feb 2025registered
Dec 2029target completion
Government Guidance Rate₹21,154/sq ydScale46 flatsAuthorityMahaRERA
10.7 km awayMixed

SAMRA ONE

SAMRA LUXURY PRIVATE LIMITED · Amravati

Dec 2025registered
Dec 2031target completion
Government Guidance Rate₹21,154/sq ydScale65 flatsAuthorityMahaRERA
11.2 km awayOthers

LIFESTYLE HOMES

LIFESTYLE HOME SPACES · Amravati

Jan 2024registered
Nov 2027target completion
Government Guidance Rate₹21,154/sq ydScale55 flatsAuthorityMahaRERA
11.7 km awayResidential / Group Housing

SHRI GIRIJATMAJ HEIGHTS

SAGAR PRAKASHRAO BUTE · Amravati

Oct 2023registered
Dec 2026target completion
Government Guidance Rate₹21,154/sq ydScale18 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.