01

Complete project overview

RAJ-RERA · Registration filing
Units
24 units
Mix
6 × Flat No. G003, 103, 203, 303, 403, 503 (G+5th Floor) (3 BHK) · 6 × Flat No. G004, 104, 204, 304, 404, 504 (G+5th Floor) (2 BHK) · 5 × Flat No. G001, 101, 201, 301, 401 (G+4th Floor) (3 BHK) · 5 × Flat No. G002, 102, 202, 302, 402 (G+4th Floor) (3 BHK) · 1 × Flat No. 501 with terrace (5th Floor) · 1 × Flat No. 502 with terrace (5th Floor)
Carpet area
75–117 sq mper-type range, as filed
Land area
1,214 sq m

Timeline

Construction startAug 2025
RERA registeredOct 2025
Proposed completionApr 2028
TodaySep 2026

Find your flat

Filed by type and size, in the batches the builder registered — not a per-flat listing. Look yours up.

24 units across 6 batches
BuildingTypeArea sq mCount
GALAXY SOLITAIREFlat No. G001, 101, 201, 301, 401 (G+4th Floor) (3 BHK)1175
GALAXY SOLITAIREFlat No. G002, 102, 202, 302, 402 (G+4th Floor) (3 BHK)1175
GALAXY SOLITAIREFlat No. G003, 103, 203, 303, 403, 503 (G+5th Floor) (3 BHK)896
GALAXY SOLITAIREFlat No. G004, 104, 204, 304, 404, 504 (G+5th Floor) (2 BHK)756
GALAXY SOLITAIREFlat No. 501 with terrace (5th Floor)1171
GALAXY SOLITAIREFlat No. 502 with terrace (5th Floor)1171

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

RAJ-RERA · Builder registration

M/S. GALAXY BUILDERS

OrganisationPromoter type
Udaipur, RajasthanBased in
1Projects
1City
2025–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
Plot No. 01, in Khasra No. 1800/607, 1802/608, 1766/1405, Shobhagpura, Shobhagpura, Girwa, Udaipur, 313011
Village
Shobhagpura
Taluka
Girwa
District
Udaipur
Pincode
313011
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 333m away · 4 clinics within 1km · Doctor's clinic within 1km
LifestyleNo parks within 2km
ShoppingSupermarket 2.0km away
Getting around
Expressway 2.1 km · Udaipur BypassPrimary road 989 mRailway line 2.9 kmRailway station 3.1km away (Ranapratap Nagar)Limited bus connectivity nearby
Water & environment
River 1.1 km · AharWater body 1.4 km · Roop Sagar
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹7.81 Cr declared to build 24 flats. What that works out to:

₹32.56 Lakhdeclared cost per flatall-in — land + construction
₹1,931/sq ftof built-up area₹20,786/sq m
10%of the cost is land₹623/sq ft of land

This is what the builder filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Government Guidance Rate

Rajasthan IGRS — DLC rates

In Rajasthan it’s called the DLC rate.

₹16,723per sq yd
₹20,000per sq m
Which rate
residential, interior plot
Matched to
The rate published for the village of “SHOBHAGPURA”.
Highest rate
₹53,420 per sq yd — the top road-facing rate among the 6 residential rates published for this village

By the road it faces

interior plot₹20,000 / sq m₹16,723 / sq yd
road-facing₹24,450 / sq m₹20,443 / sq yd
41–60 ft road₹28,080 / sq m₹23,478 / sq yd
61–99 ft road₹30,620 / sq m₹25,602 / sq yd
100 ft+ road₹30,620 / sq m₹25,602 / sq yd

The same land, priced by the width of the road it faces — each band the middle of the residential rates published for this village.

What this number is — and isn’t

  • The minimum value Rajasthan’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
  • Not a market price. Sales normally register above it, and how far above varies by place and by project.
  • Its fit depends on the grain the state publishes at. This one is matched at the level of village, and says so above. How Horizon decides what to show.
05

Planning authority

RAJ-RERA · Approved building plan
Building Permitapproved 17 Oct 2025 · 11 mo ago
The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

07

Other projects nearby

The register · within 25 km

50 residential projects still under way within 25 km. Step out ring by ring:

4 projects within 1 km — showing the nearest 4.

UdaipurGroup Housing

Mandot Prime

Nirvan Enterprises

Feb 2024registered
Jan 2028target completion
Declared cost₹14.51 CrScale24 flatsAuthorityRAJ-RERA
GirwaGroup Housing

URBAN HEIGHTS

URBAN HEIGHTS

Mar 2024registered
Dec 2026target completion
Declared cost₹6.11 CrScale20 flatsAuthorityRAJ-RERA
UdaipurMixed (Residential And Commercial)

MUNDRA EDGE

Mundra dream homes pvt. Ltd.

Jul 2025registered
Sep 2026target completion
Declared cost₹15.00 CrScale29 flatsAuthorityRAJ-RERA
GirwaGroup Housing

SHREEJI EXOTICA PHASE 2

SHREEJI DEVELOPERS

Sep 2023registered
Jun 2027target completion
Declared cost₹44.95 CrScale71 flatsAuthorityRAJ-RERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. This project’s coordinate is approximate, so distances are rough.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.