01

Complete project overview

RAJ-RERA · Registration filing
Project name
GANESH VIHAR 1st B- BLOCK
Plots
99 plots
Land area
17,025 sq m
Description
1. As per Township Policy 2010, 10 Plots (Plot No. 6, 7, 18, 19, 32, 33, 46, 47, 51 And 52) having Total area of 1360.48 Sq. Mtrs equalling to 12.5% have been kept mortgage. These plots would be allotted after the internal development work is completed and development charges are deposited with Nagar Palika Chaksu. 2. The Total Open Area includes (Park +SWM +Mobile Tower + Public Utility + Road ) Mtr is 6151.57 Square meters

Timeline

Construction startJun 2025
RERA registeredAug 2025
Proposed completionOct 2026
TodaySep 2026

Find your plot

Filed by type and size, in the batches the builder registered — not a per-plot listing. Look yours up.

99 plots across 39 batches
TypeArea sq mCount
Plot1411
Plot1051
Plot1001
Plot941
Plot891
Plot871
Plot1411
Plot1028
Plot1303
Plot1661
Plot921
Plot9322
Plot1184
Plot1121
Plot1451
Plot1581
Plot1141
Plot1301
Plot1871
Plot1591
Plot2201
Plot1237
Plot1351
Plot1201
Plot1251
Plot1301
Plot1371
Plot1095
Plot1195
Plot1422
Plot1195
Plot1521
Plot2331
Plot1411
Plot1351
Plot1291
Plot1231
Plot1481
Plot99

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each size exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

RAJ-RERA · Builder registration

NITIN KEDIA

IndividualPromoter type
Jaipur, RajasthanBased in
2Projects
1City
2025–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
199 plotson the public record across 2 projects
35,225 sq mplotted area
35,225 sq mland declared
₹28.94 Crdeclared build cost

Build cost is what the builder declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from NITIN KEDIA— the full portfolio →

03

Location & price analysis

RAJ-RERA · Registration filing
Address
10158,10159,10160,10161,10162,10163, 10130 MIN AND 10131 MIN, CHAKSU WEST, Chaksu, Jaipur, 300000
Village
CHAKSU WEST
Taluka
Chaksu
District
Jaipur
Pincode
300000
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 301m away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 3.4 kmPrimary road 3 mRailway line 3.8 kmRailway station 3.8km away (Chaksu)Limited bus connectivity nearby
Price analysisdeclared build cost — not a sale price

₹4.82 Cr declared to build 99 plots. What that works out to:

₹4.87 Lakhdeclared cost per plotall-in — land + construction
₹263/sq ftof plotted area₹2,830/sq m
44%of the cost is land₹115/sq ft of land

This is what the builder filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Government Guidance Rate

Rajasthan registration department

In Rajasthan it’s called the DLC rate.

No government guidance rate is shown for this project.

Rajasthan's schedule is in Horizon's record, but this project's filed location couldn't be matched to one place with certainty — so no figure is shown rather than a guess.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

RAJ-RERA · Approved building plan
Layout Permitapproved 13 Aug 2025 · 1 yr ago
The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

07

Other projects nearby

The register · within 25 km

55 plotted projects still under way within 25 km. Step out ring by ring:

13 projects within 1 km — showing the nearest 6.

ChaksuPlotted Development

SWARN BHOOMI UDAY GAJRAJ

UDAI GAJRAJ REAL ESTATE LLP

Oct 2024registered
Dec 2026target completion
possession revisedDeclared cost₹7.64 CrScale142 plotsAuthorityRAJ-RERA
ChaksuPlotted Development

VATSALYA ENCLAVE

ASHOK JAIN

Oct 2024registered
Mar 2026target completion
possession revisedDeclared cost₹1.62 CrScale31 plotsAuthorityRAJ-RERA
ChaksuPlotted Development

THE SOUTHERN CITY

RIYASAT INFRATECH DEVELOPERS LLP

Jan 2025registered
May 2026target completion
Declared cost₹16.23 CrScale75 plotsAuthorityRAJ-RERA
ChaksuPlotted Development

GANESH VIHAR 1st A-BLOCK

AJAY BHATI

Aug 2025registered
Sep 2026target completion
Declared cost₹2.50 CrScale110 plotsAuthorityRAJ-RERA
ChaksuPlotted Development

SOUTH VALLEY

PRASHANT MAAMODIA

Aug 2025registered
Dec 2026target completion
Declared cost₹5.09 CrScale89 plotsAuthorityRAJ-RERA
ChaksuPlotted Development

UDAY NARAYAN VIHAR.,

RAJENDRA CHOUDHARY

Sep 2025registered
Dec 2026target completion
Declared cost₹26.09 CrScale144 plotsAuthorityRAJ-RERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. This project’s coordinate is approximate, so distances are rough.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.