HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
9
Buildings
4
Parking
75 spaces
Land area
1,439 sq m
Sanctioned built-up
4,998 sq m

Timeline

RERA registeredFeb 2024
Proposed completionMar 2027
TodayJul 2026
Construction progress
Podiums0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Landscaping & Tree…0%
Treatment And Disp…0%
Solid Waste Manage…0%
Fire protection an…0%
Electrical meter r…0%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Superstructure100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

GIRIVIHAR DEVELOPERS

PartnershipPromoter type
Raigarh, MAHARASHTRABased in
1Projects
1City
2024–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Karjat
Taluka
Karjat
District
Raigarh
Pincode
410201
Survey no.
174/20/A/1 AND 174/20/A/2
North boundary
CTS NO 174 20 A
East boundary
CTS NO 174 26
South boundary
ROAD
West boundary
CTS NO 174 31 K CTS 174 31 B
What’s nearby
SchoolsNo schools within 2km · Library 134m away
HealthcareHospital 39m away · 4 clinics within 1km
Lifestyle2 parks within 500m
ShoppingNo supermarket within 2km · Bank 407m away
Getting around
Expressway 373 mPrimary road 1.2 km · Karjat RoadRailway line 435 mRailway station 431m away (Karjat)Limited bus connectivity nearby
Water & environment
River 91 m · UlhasWater body 3.1 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Karjat Municipal Council

Municipal Council
Building Permit
Survey no. 174/20/A/1 AND 174/20/A/2
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Karjat Municipal Council

Municipal corporation

Has approved 31 RERA projects0.2% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
28
On record
76 flats · 0 plots
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.