Complete project overview

MahaRERA · Registration filing
Floors
21
Buildings
2
Parking
62 spaces
Land area
400 sq m
Sanctioned built-up
5,026 sq m

Timeline

RERA registeredJun 2024
Proposed completionDec 2026
TodayJul 2026
Construction progress
Podiums0%
Flat fit-out0%
OC-readiness0%
Water Supply0%
Storm Water Drains0%
Fire protection an…0%
Electrical meter r…0%
Stairs & lifts50%
External finishes50%
Internal finishes60%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Superstructure100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

NIDHAAN REALTY LLP

PartnershipPromoter type
Mumbai Suburban, MAHARASHTRABased in
1Projects
1City
2024–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Mogra
Taluka
Andheri
District
Mumbai Suburban
Pincode
400069
Survey no.
175A ,183C
North boundary
By CTS 183 B DP Road
East boundary
By CTS Nos 183 C Partpartly by Balance 70 of t
South boundary
by Balance 70 of the Larger Property CTS No 175A
West boundary
By CTS Nos 182
What’s nearby
Schools1 school within 500m · College or university 1.1km away
HealthcareHospital 571m away · 8 clinics within 1km · Doctor's clinic within 1km
LifestylePark 598m away · 12+ restaurants and cafes within 1km · Swimming pool within 2km
ShoppingSupermarket 1.4km away · Convenience store within 1km
Getting around
Expressway 74 m · Western Express HighwayPrimary road 935 m · Swami Vivekanand RoadRailway line 864 mMetro station 424m away (Mogra)Bus stop within 500m
Water & environment
Water body 1.7 km · Lokmanya Tilak Ganesh Visarjan Talao
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Municipal Corporation of Greater Mumbai

Municipal Corporation · MCGM
Building Permit
Survey no. 175A ,183C
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation of Greater Mumbai

Municipal corporation

Has approved 2,862 RERA projectsabout 1 in 7 in Maharashtra, more than any other body in the state.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
2,166
On record
34,498 flats · 0 plots
Reach
9 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
EncumbranceDeclared financial encumbrance on the project
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.