HORIZONMarkets
01

Complete project overview

RERA Punjab · Registration filing
Parking
267 spaces
Land area
12,877 sq m

Timeline

Project startedDec 2023
Proposed completionDec 2028
TodayJul 2026
02

Builder’s track record

RERA Punjab · Promoter registration

BOHRR INFRA (Other than Individual)

PartnershipsPromoter type
1Projects
1Cities
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Punjab · Registration filing
District
Ludhiana
Planning zone
Zone 3 - Ludhiana (within and outside municipal limits upto 15 Kms.)
Address
Village Daad , Hadbast No. 279 Ludhiana East , Ludhiana , Punjab - 142022
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 1.3km away · Clinic within 2km
LifestylePark 1.9km away · Gym or sports centre 1.5km away
ShoppingNo supermarket within 2km · Convenience store within 500m
Getting around
Expressway 3.4 km · Ferozepur Road FlyoverPrimary road 3.7 km · Ferozepur Road FlyoverRailway line 2.8 kmRailway station 4.7km away (Model Gram)Limited bus connectivity nearby
Water & environment
Canal 3.5 km · Sidhwan Canal
distances only — not a flood assessment
Declared external development
Solid waste0%
Electricity0%
Sewage0%
Water supply0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
Land, title & encumbrance
Land ownershipDeclared fully owned by the promoter
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
Price analysisdeclared build cost — not a sale price

₹19.82 Cr declared. What that works out to:

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RERA Punjab · Approved building plan
Building Permit
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Punjab does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Punjab does not publish a complaints register. This read cannot speak to them either way.