Timeline

RERA registeredAug 2025
Proposed completionMar 2026
TodayJul 2026
Construction progress
Aggregate area of …35%
Water conservation…80%
Water Supply90%
Community Building…95%
Storm Water Drains97%
Landscaping & Tree…98%
Internal Roads & F…100%
Sewerage (Chamber,…100%
Street Lighting100%
Treatment And Disp…100%
Solid Waste Manage…100%
Fire protection an…100%
Electrical meter r…100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Maan-Hinje Township Developers Private Limited

CompanyPromoter type
Mumbai Suburban, MAHARASHTRABased in
3Projects
1City
2025–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
44 plotson the public record across 3 projects
3,69,875 sq mbuilt-up filed
17,208 sq mplotted area
81,175 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Hinjavadi (CT)
Taluka
Mulshi
District
Pune
Pincode
411057
Survey no.
198/1/1 (P), 198/1/2 (P), 196/3 (P)
North boundary
18m Wide DP Road
East boundary
S. No. 195/3
South boundary
S. No. 196/4, S. No. 198/2
West boundary
S. No. 198/1/1 (P), S. No. 198/2 & S. No. 197
What’s nearby
SchoolsNo schools within 2km · College or university 1.1km away · Library 1.2km away
HealthcareHospital 1.9km away · 1 clinic within 1km · Pharmacy within 1km
LifestylePark 836m away · Gym or sports centre 1.6km away · 24+ restaurants and cafes within 1km
ShoppingSupermarket 874m away · Convenience store within 1km · Bank 856m away
Getting around
Expressway 3.4 kmPrimary road 670 m · Maan RoadMetro station 2.0km away (Hinjawadi)Bus stop within 1km
Water & environment
Water body 1.0 kmRiver 1.1 km · Mula
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Pune Metropolitan Region Development Authority

Metropolitan Development Authority
Layout Permit
Survey no. 198/1/1 (P), 198/1/2 (P), 196/3 (P)

The promised possession date (31 Mar 2026) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Pune Metropolitan Region Development Authority

Metropolitan / development authority

Has approved 1,013 RERA projectsabout 1 in 20 in Maharashtra.

an apartments market87% apartments · 13% plotted layouts. Layouts like yours are the smaller share here — this body mostly approves apartments.

Builders
604
On record
21,940 flats · 10,299 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
EncumbranceDeclared financial encumbrance on the project
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.