HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
23
Buildings
12
Parking
3,783 spaces
Land area
17,531 sq m
Sanctioned built-up
48,156 sq m
Recreational open space
620 sq m

Timeline

RERA registeredNov 2020
Proposed completionMar 2025
TodayJul 2026
Construction progress
Stilt floor0%
Excavation100%
Basement (if any)100%
Podiums100%
Plinth100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Internal Roads & F…100%
Water Supply100%
Sewerage (Chamber,…100%
Storm Water Drains100%
Landscaping & Tree…100%
Street Lighting100%
Community Building…100%
Treatment And Disp…100%
Solid Waste Manage…100%
Water conservation…100%
Energy managemcnt100%
Fire protection an…100%
Electrical meter r…100%
Aggregate area of …100%
Open Parking100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Mahalunge Township Developers Private Limited

CompanyPromoter type
Mumbai Suburban, MAHARASHTRABased in
8Projects
1City
2020–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
8 projectson the public record across 8 projects
4,18,077 sq mbuilt-up filed
1,08,008 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Mahalunge
Taluka
Mulshi
District
Pune
Pincode
411045
Survey no.
Sector R7- Survey No 41/4, 42/6, 42/7, 42/8, 42/9 and 42/10
North boundary
Part of Survey No 42
East boundary
Proposed 12M wide pedestrian street
South boundary
36M wide road
West boundary
Proposed 30M wide road
What’s nearby
SchoolsNearest school 1.9km away · Library 1.2km away
HealthcareHospital 1.5km away · 1 clinic within 1km
LifestylePark 2.0km away · Gym or sports centre 1.8km away · Swimming pool within 2km
ShoppingSupermarket 1.6km away · Bank 91m away · ATM within 500m
Getting around
Expressway 759 mPrimary road 884 m · exit to banerMetro station 866m away (Balewadi Stadium)4 bus stops within 500m
Water & environment
Water body 301 mRiver 556 m · Mula
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Pune Metropolitan Region Development Authority

Metropolitan Development Authority
Building Permit
Survey no. Sector R7- Survey No 41/4, 42/6, 42/7, 42/8, 42/9 and 42/10

The promised possession date (30 Mar 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Pune Metropolitan Region Development Authority

Metropolitan / development authority

Has approved 1,013 RERA projectsabout 1 in 20 in Maharashtra.

an apartments market87% apartments · 13% plotted layouts. Apartments like yours are this body's core business.

Builders
604
On record
21,940 flats · 10,299 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
Litigation3 cases on record, earliest 2014
EncumbranceDeclared financial encumbrance on the project
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

5 complaints on MahaRERA’s register for this project 1 disposed, 4 still open.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.