MahaRERA · Registration filing
Floors
8
Buildings
2
Parking
57 spaces
Land area
2,020 sq m
Sanctioned built-up
2,337 sq m

Timeline

RERA registeredAug 2023
Proposed completionJun 2025
TodayJul 2026
02

Builder’s track record

MahaRERA · Promoter registration

SEEMA VIJAY NIKAM

IndividualPromoter type
Raigarh, MAHARASHTRABased in
2Projects
2Cities
2017–2025Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
30 homeson the public record across 2 projects
3,215 sq mbuilt-up filed
2,920 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Ajivali
Taluka
Panvel
District
Raigarh
Pincode
410221
Survey no.
Survey No- 163
North boundary
Survey No- 164
East boundary
Survey No- 162
South boundary
Survey No- 159-2
West boundary
Survey No-165
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 4.2km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 320 mPrimary road 1.5 kmRailway line 1.2 km · Panvel Junction - Karjat JunctionRailway station 2.2km away (Somatne)Limited bus connectivity nearby
Water & environment
Water body 964 mRiver 1.4 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Maharashtra State Road Development Corporation Limited

Building Permit
Survey no. Survey No- 163

The promised possession date (30 Jun 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Maharashtra State Road Development Corporation Limited

Planning authority

Has approved 32 RERA projects0.2% of Maharashtra.

an apartments market91% apartments · 9% plotted layouts. Apartments like yours are this body's core business.

Builders
27
On record
84 flats · 842 plots
Since
2018

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.