Complete project overview

MahaRERA · Registration filing
Floors
8
Buildings
2
Parking
47 spaces
Land area
2,027 sq m
Sanctioned built-up
2,027 sq m

Timeline

RERA registeredJul 2023
Proposed completionDec 2027
TodayJul 2026
Construction progress
Basement (if any)0%
Podiums0%
Street Lighting0%
Open Parking0%
Electrical meter r…50%
Excavation100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Internal Roads & F…100%
Water Supply100%
Sewerage (Chamber,…100%
Storm Water Drains100%
Water conservation…100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

MAHALAXMI HOMES

PartnershipPromoter type
Palghar, MAHARASHTRABased in
1Projects
1City
2023–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Makane
Taluka
Palghar
District
Palghar
Pincode
401102
Survey no.
G NO 227/PT
North boundary
AMENITY CENTER
East boundary
GUT NO 224
South boundary
BLDG NO 1
West boundary
LAYOUT ROAD
What’s nearby
SchoolsNearest school 1.0km away
HealthcareHospital 179m away · 4 clinics within 1km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km · Bank 49m away
Getting around
Expressway 1.1 kmPrimary road 813 mRailway line 255 mRailway station 247m away (Palghar)Limited bus connectivity nearby
Water & environment
Water body 665 m · Water TankRiver 2.2 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Collector, Palghar

Collector office
Building Permit
Survey no. G NO 227/PT
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

The planning authority

The body that sanctioned this project. It has approved 4,607 RERA projects across 33 districts about 1 in 4 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.