HORIZONMarkets
Registration lapsed

This project’s MahaRERA registration has lapsed— it expired and was not renewed. A lapsed project may be stalled, finished-but-not-updated, or abandoned; the record stops here and RERA’s ongoing protections may no longer apply. Confirm the current status directly with MahaRERA before you rely on anything below.

01

Complete project overview

MahaRERA · Registration filing
Units
72 units
Mix
36 × 2 BHK · 36 × 1 RK
Carpet area
20–93 sq mper-unit range, as filed
Floors
3
Buildings
5
Parking
5 spaces
Land area
4,222 sq m
Sanctioned built-up
3,204 sq m

Timeline

RERA registeredSep 2020
Proposed completionSep 2024
TodayJul 2026

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

72 units across 7 batches
TypeArea sq mCount
2 BHK934
2 BHK6024
2 BHK884
1 RK2212
2 BHK572
2 BHK882
1 RK2024

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

MahaRERA · Promoter registration

THEPADE BUILDERS

PartnershipPromoter type
Jalgaon, MAHARASHTRABased in
1Projects
1City
2020–2024Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Pungaon
Taluka
Pachora
District
Jalgaon
Pincode
424201
Survey no.
Plot No 50 to 53, Plot No 54/1 to Plot No 54/10 out of Gat No 122/1 and Plot No 30/1 to Plot No 30/20 out of Gat No 122/1 and Plot No 47/48/53/54 out of Gat No 117/2
North boundary
6 Metre Road
East boundary
9 Metre Road
South boundary
6 Metre Road
West boundary
6 Metre Road
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 138m away · 6 clinics within 1km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 635 mPrimary road 2.2 kmRailway line 434 m · Mumbai–Nagpur lineRailway station 870m away (Pachora Junction)Limited bus connectivity nearby
Water & environment
River 932 m · Hivara
distances only — not a flood assessment
Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.