Complete project overview
RAJ-RERA · Registration filing- Land area
- 2,499 sq m
- Completion deadline extended
- 1 extension on record — latest to 30 Jun 2019declared reason: other than force majeure
- Description
- "Grand Koela's Orient lake View Apartments is constructed under registered development agreement with the landowners and 50% of the constructed flats will be consideration of the landowners. Project is approved by bhawan nirmaan samiti , but approved map was not issued, therefore hon'able court given the permission on deemed approval basis as per the map submitted to nagar nigam , kota All approved building sanction drawings have been uploaded under the head of copy of layout approvals and building approvals
Timeline
Builder’s track record
RAJ-RERA · Promoter registrationOrient Builders and Developers A unit of Swan Industries Pvt Ltd
Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.
Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
Location & price analysis
RAJ-RERA · Registration filing- Address
- 0, KOELA HOUSE, RAMPURA, SAROVBAR ROAD, OLD DHANMANDI, KOTA, Ladpura, Kota, 324006
- Village
- KOTA
- Taluka
- Ladpura
- District
- Kota
- Pincode
- 324006
₹30.00 Cr declared. What that works out to:
This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.
Planning authority
RAJ-RERA · Approved building planThe promised possession date (30 Jun 2018) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.
A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.
What this record cannot tell you
- Build quality — no filing records how well it was actually built.
- Private disputes — only complaints escalated to the authority appear here.
- What it will be worth — the record is the past; it does not price the future.
- Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
- Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.