RAJ-RERA · Registration filing
Land area
1,121 sq m
Completion deadline extended
1 extension on record — latest to 30 Jun 2019declared reason: other than force majeure
Description
Orient Apex project is under construction through a registered development agreement with landowners and 50% share of constructed flats will be landowner's consideration. All approved building sanction drawings have been uploaded under the head of copy of layout approvals and building approvals.

Timeline

Construction startJan 2016
RERA registeredOct 2017
Proposed completionJun 2018
TodayJul 2026
02

Builder’s track record

RAJ-RERA · Promoter registration

Orient Builders and Developers A unit of Swan Industries Pvt Ltd

OrganisationPromoter type
Kota, RajasthanBased in
2Projects
1City
2017–2018Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
2 projectson the public record across 2 projects
9,647 sq mbuilt-up filed
3,620 sq mland declared
₹40.84 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
3, BALAJI MARKET YOJNA, KOTA, Ladpura, Kota, 324005
Village
KOTA
Taluka
Ladpura
District
Kota
Pincode
324005
What’s nearby
SchoolsNo schools within 2km · College or university 1.5km away · Library 1.7km away
HealthcareHospital 123m away · 3 clinics within 1km · Doctor's clinic within 1km
LifestyleNo parks within 2km · Gym or sports centre 1.6km away
ShoppingSupermarket 1.5km away
Getting around
Expressway 2.4 km · Kota BypassPrimary road 2.2 kmRailway line 3.4 km · Mumbai - Delhi RailwayRailway station 3.6km away (Dakaniya Talav)Limited bus connectivity nearby
Water & environment
Canal 177 mWater body 966 m
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹10.84 Cr declared. What that works out to:

50%of the cost is land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan
Building Permitapproved 30 Oct 2017 · 8 yrs ago

The promised possession date (30 Jun 2018) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.