HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
9
Buildings
2
Parking
139 spaces
Land area
1,257 sq m
Sanctioned built-up
3,435 sq m

Timeline

RERA registeredDec 2022
Proposed completionOct 2024
TodayJul 2026
02

Builder’s track record

MahaRERA · Promoter registration

Shree Hinglajmata Constructions

PartnershipPromoter type
Aurangabad, MAHARASHTRABased in
1Projects
1City
2022–2024Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Aurangabad (M Corp.)
Taluka
Aurangabad
District
Aurangabad
Pincode
431003
Survey no.
138
North boundary
Plot No 137
East boundary
11 m Wide Road
South boundary
24 m Wide Road
West boundary
Survey No 16
What’s nearby
Schools1 school within 500m · 3 educational institutions within 1km · College or university 570m away
HealthcareHospital 177m away · 5 clinics within 1km
LifestylePark 822m away · 7 restaurants and cafes within 1km
ShoppingSupermarket 1.8km away · Mall 802m away · Convenience store within 500m
Getting around
Expressway 181 m · Jalna RoadPrimary road 1.6 km · Kranti ChowkRailway line 2.7 kmRailway station 3.1km away (Mukundawadi)Bus stop within 500m
04

Planning authority

MahaRERA · Approved building plan

Chhatrapati Sambhajinagar Municipal Corporation

Municipal Corporation
Building Permit
Survey no. 138

The promised possession date (6 Oct 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Chhatrapati Sambhajinagar Municipal Corporation

Municipal corporation

Has approved 33 RERA projects0.2% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
30
On record
78 flats · 0 plots
Since
2021

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.