HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
6
Buildings
2
Parking
6 spaces
Land area
2,338 sq m
Sanctioned built-up
4,208 sq m

Timeline

RERA registeredApr 2021
Proposed completionDec 2025
TodayJul 2026
Construction progress
Podiums0%
OC-readiness5%
Flat fit-out10%
External finishes10%
Internal finishes50%
Stairs & lifts50%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Superstructure100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

M V REALITIES

PartnershipPromoter type
Ahmednagar, MAHARASHTRABased in
1Projects
1City
2021–2025Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Ahmadnagar (M Corp.)
Taluka
Nagar
District
Ahmednagar
Pincode
414001
Survey no.
TP 4 FINAL PLOT NO 33 SUB PLOT 59 TO 63
North boundary
NALA
East boundary
NALA AND PLOT NO 1
South boundary
PLOT NO 64 AND 9 MTR WIDE ROAD
West boundary
10 MTR WIDE ROAD
What’s nearby
SchoolsNearest school 1.2km away · 3 educational institutions within 1km · College or university 285m away
HealthcareHospital 117m away · 1 clinic within 1km · Pharmacy within 1km
Lifestyle1 park within 500m
ShoppingNo supermarket within 2km · Bank 290m away
Getting around
Expressway 1.7 kmPrimary road 239 m · Ahmednagar Loni Dhanora RoadRailway line 2.8 kmRailway station 4.1km away (Ahmadnagar)Limited bus connectivity nearby
Water & environment
River 663 mWater body 1.3 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Ahemednagaer Municipal Corporation

Municipal Corporation
Building Permit
Survey no. TP 4 FINAL PLOT NO 33 SUB PLOT 59 TO 63

The promised possession date (31 Dec 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation

A city municipal corporation that sanctions projects within its own limits. It has approved 12,653 RERA projects across 34 districts about 1 in 2 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.