HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
24
Buildings
2
Parking
1 spaces
Land area
12,790 sq m
Sanctioned built-up
21,899 sq m
Recreational open space
1,229 sq m

Timeline

RERA registeredDec 2023
Proposed completionDec 2030
TodayJul 2026
Construction progress
Podiums0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Street Lighting0%
Community Building…0%
Treatment And Disp…0%
Solid Waste Manage…0%
Water conservation…0%
Energy managemcnt0%
Fire protection an…0%
Electrical meter r…0%
Aggregate area of …0%
Open Parking0%
Internal finishes10%
Flat fit-out17%
Superstructure28%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Haware Properties LLP

PartnershipPromoter type
Thane, MAHARASHTRABased in
10Projects
2Cities
2023–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
10 projectson the public record across 10 projects
1,35,963 sq mbuilt-up filed
81,090 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Thane Municipal CorporationMunicipal Corporationthis project4 of 10 projects
District Collector ThaneCollector office2 of 10 projects
Thane Collector OfficeCollector office2 of 10 projects
District Collector Office ThaneCollector office1 of 10 projects
Maharashtra State Road Development Corporation1 of 10 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Thane (M Corp.)
Taluka
Thane
District
Thane
Pincode
410203
Survey no.
86/3,87/1A,87/2A,87/2B,89/1
North boundary
12m wide internal road
East boundary
Haware My First Home Shil Phata Phase 1
South boundary
Sana Hill Apartment
West boundary
Hira Residency
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 2.0km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km · Convenience store within 1km
Getting around
Expressway 208 mPrimary road 223 m · Shil Phata Mahape RoadRailway line 3.9 km · Trans-Harbour LineRailway station 4.5km away (Nilaje)2 bus stops within 500m
Water & environment
Water body 687 m · Shweta
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Thane Municipal Corporation

Municipal Corporation
Building Permit
Survey no. 86/3,87/1A,87/2A,87/2B,89/1
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Thane Municipal Corporation

Municipal corporation

Has approved 489 RERA projects2.4% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
318
On record
7,890 flats · 0 plots
Reach
5 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.