HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
24
Buildings
2
Parking
107 spaces
Land area
2,837 sq m
Sanctioned built-up
11,603 sq m

Timeline

RERA registeredMar 2025
Proposed completionDec 2029
TodayJul 2026
Construction progress
Basement (if any)0%
Podiums0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Street Lighting0%
Solid Waste Manage…0%
Water conservation…0%
Fire protection an…0%
Electrical meter r…0%
Open Parking0%
Superstructure42%
Excavation100%
Plinth100%
Stilt floor100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

M M DEVELOPERS

PartnershipPromoter type
Palghar, MAHARASHTRABased in
11Projects
7Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
531 homes · 176 plotson the public record across 11 projects
42,141 sq mbuilt-up filed
16,447 sq mland declared
₹43.85 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Bhavnagar Municipal CorporationMunicipal / Corporation2 of 6 projects
Others1 of 6 projects
Pune Metropolitan Region Development AuthorityMetropolitan Development Authority1 of 6 projects
Vapi MunicipalityMunicipal / Corporation1 of 6 projects
Vasai Virar City Municipal CorporationMunicipal Corporationthis project1 of 6 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
District
Palghar
Pincode
401208
Survey no.
S no 155, H no 3
North boundary
S NO 155 PART
East boundary
S NO 156 PART
South boundary
M W ROAD D P ROAD
West boundary
S NO 330 PART
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 603m away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 286 mPrimary road 2.5 km · Vasai RoadNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
River 529 mCanal 1.3 kmWater body 1.6 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Vasai Virar City Municipal Corporation

Municipal Corporation
Building Permit
Survey no. S no 155, H no 3
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Vasai Virar City Municipal Corporation

Municipal corporation

Has approved 627 RERA projects3.1% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
513
On record
8,010 flats · 60 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.