Complete project overview

MahaRERA · Registration filing
Floors
28
Buildings
2
Parking
90 spaces
Land area
635 sq m
Sanctioned built-up
3,507 sq m
Recreational open space
3,428 sq m

Timeline

RERA registeredJun 2019
Proposed completionDec 2026
TodayJul 2026
Construction progress
Podiums0%
Landscaping & Tree…5%
Flat fit-out8%
Street Lighting10%
OC-readiness20%
Internal Roads & F…40%
Water conservation…50%
Energy managemcnt50%
Fire protection an…50%
Aggregate area of …50%
Open Parking50%
External finishes51%
Storm Water Drains60%
Stilt floor68%
Water Supply70%
Sewerage (Chamber,…70%
Community Building…70%
Stairs & lifts86%
Electrical meter r…90%
Excavation100%
Basement (if any)100%
Plinth100%
Superstructure100%
Internal finishes100%
Treatment And Disp…100%
Solid Waste Manage…100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

SIDDHI REAL ESTATE DEVELOPERS

PartnershipPromoter type
Thane, MAHARASHTRABased in
6Projects
1City
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
559 homeson the public record across 6 projects
32,864 sq mbuilt-up filed
3,489 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Thane Municipal Corporation (Tmc)Municipal Corporationthis project1 of 2 projects
Thane Municipal Corporation, ThaneMunicipal Corporation1 of 2 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Thane (M Corp.)
Taluka
Thane
District
Thane
Pincode
400608
Survey no.
Survey No 46/18 Part
North boundary
20 METER WIDE DP ROAD
East boundary
WING E
South boundary
PODIUM
West boundary
WING C
What’s nearby
SchoolsNearest school 1.9km away · Library 1.5km away
HealthcareHospital 674m away · 1 clinic within 1km
LifestylePark 1.7km away · Gym or sports centre 1.9km away · 5 restaurants and cafes within 1km
ShoppingSupermarket 771m away · Bank 861m away
Getting around
Expressway 265 mPrimary road 781 m · Eastern Express TurnpikeRailway line 1.7 kmMetro station 860m away (Kapurbawdi Station)13 bus stops within 500m
Water & environment
Water body 403 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Thane Municipal Corporation (Tmc)

Municipal Corporation
Building Permit
Survey no. Survey No 46/18 Part
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation

A city municipal corporation that sanctions projects within its own limits. It has approved 12,653 RERA projects across 34 districts about 1 in 2 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
Litigation6 cases on record, earliest 2009
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.