Complete project overview

K-RERA · Registration filing
Units
526 units
Mix
150 × 3BHK · 106 × 2BHK · 99 × Others-Others-Others-2BHK + S · 70 × 1BHK · 50 × Others-Others-Others-4BHK + L · 50 × Others-Others-Others-3BHK + L
Booked
486 of 526 filed sold/bookedas declared in the RERA filing
Buildings
1
Land area
35,003 sq m
Floor area
1,17,990 sq m
Description
HiLITE OLYMPUS

Timeline

Project startedJun 2022
RERA registeredJul 2022
Proposed completionDec 2026
TodayJul 2026
Construction progress

82% overall, as filed

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Sanitary Fittings72%
Electrical Fittings90%
Installation of lifts, water pumps etc95%
Fire Fighting Fittings and Equipment95%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings98%
The external plumbing and external plastering98%
Staircases, Lifts Wells99%
Excavation100%
Basement(s) and Plinth100%
Slabs of Super Structure100%
Overhead and Underground Water Tanks.100%
Completion of terraces floor each building100%
Per-activity completion % from the promoter's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

40 of 526 available
TypeArea sq mAvailable
Others-Others-Others-4BHK + L1911 of 25
3BHK1131 of 25
Others-Others-Others-3BHK + L1564 of 25
Others-Others-Others-2BHK + S995 of 25
3BHK1131 of 25
3BHK1154 of 25
Others-Others-Others-3BHK + L1582 of 25
Others-Others-Others-2BHK + S993 of 25
3BHK1123 of 25
Others-Others-Others-4BHK + L19210 of 25
2BHK811 of 25
1BHK560 of 18
1BHK550 of 20
2BHK780 of 25
3BHK1131 of 25
2BHK550 of 6
Others-Others-Others-2BHK + S991 of 25
2BHK780 of 25
1BHK550 of 12
2BHK810 of 25
1BHK550 of 20
Others-Others-Others-2BHK + S992 of 24
Others-Others-Others-2BHK S990 of 1
3BHK1131 of 25

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system.

02

Builder’s track record

K-RERA · Promoter registration

HiLITE Builders Pvt Ltd

CompanyPromoter type
Kozhikode, KeralaBased in
Yes — the promoter declared prior project experienceDeclared prior experience
6Projects
1Cities
2021–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
726 homeson the public record across 6 projects
1,70,483 sq mbuilt-up filed
50,255 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

K-RERA · Registration filing
Street
Iringalloor
Village
OLAVANNA
Taluk
Kozhikode
District
Kozhikode
Pincode
673014
Survey no.
35/16,35/17,35/65,35/24,35/32,35/29,35/59,35/21,35/62,35/63,34/41,35/14,34/8,34/10,34/12,34/58,34/36,34/51,34/59,34/57,34/67,34/62,33/6,34/13,34/65,34/21,34/22,34/23,34/37,34/38,34/39,34/40,34/56,34/14,33/25,33/35,34/35,33/18,33/42,26/62,26/63,26/15,26/17,26/5,34/61,34/11,26/3,26/69, 26/70,34/15
Patta no.
5590
What’s nearby
Schools2 schools within 1km · 3 educational institutions within 1km · College or university 1.4km away
HealthcareHospital 259m away · 1 clinic within 1km
LifestylePark 897m away · 8 restaurants and cafes within 1km
ShoppingSupermarket 1.7km away · Mall 550m away · Bank 792m away
Getting around
Expressway 201 m · Kannur-Calicut-Valanchery HighwayPrimary road 3.3 km · Mini Byepass RoadNo metro or railway within 5kmBus stop within 1km
Water & environment
Water body 737 m · Aanchiyil KulamRiver 890 m · Mampuzha River
distances only — not a flood assessment
Land, title & encumbrance
Land ownershipBuilt on land that includes third-party owners — a landowner (joint-development) arrangement is declared; confirm the title and your share
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
04

Planning authority

K-RERA · Approved building plan

Olavanna Grama Panchayat

Grama Panchayat
approved 18 Jun 2022 · 4 yrs ago
Building Permit no. A4-BA(202443)/2022Survey no. 35/16,35/17,35/65,35/24,35/32,35/29,35/59,35/21,35/62,35/63,34/41,35/14,34/8,34/10,34/12,34/58,34/36,34/51,34/59,34/57,34/67,34/62,33/6,34/13,34/65,34/21,34/22,34/23,34/37,34/38,34/39,34/40,34/56,34/14,33/25,33/35,34/35,33/18,33/42,26/62,26/63,26/15,26/17,26/5,34/61,34/11,26/3,26/69, 26/70,34/15
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan A4-BA(202443)/2022 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

Olavanna Grama Panchayat

Grama panchayat

Has approved 16 RERA projects1% of Kerala.

an apartments market94% apartments · 6% plotted layouts. Apartments like yours are this body's core business.

Builders
10
On record
2,233 flats · 23 plots
Since
2021

More apartment-heavy than Kerala overall — 94% apartments here vs 81% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — K-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — K-RERA does not publish a complaints register. This read cannot speak to them either way.