HORIZON
Share

INDIRA GOPAL

PM1290002601332 · MahaRERA · https://gethorizon.in/projects/indira-gopal-sawantpur-palus-ewmpip56

01

Complete project overview

MahaRERA · Registration filing
Units
71 units
Floors
7
Buildings
6
Parking
122 spaces
Land area
2,582 sq m
Sanctioned built-up
5,601 sq m

Timeline

RERA registeredJul 2026
Proposed completionDec 2030
TodaySep 2026
Construction progress
Excavation0%
Plinth0%
Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Street Lighting0%
Electrical meter r…0%
Aggregate area of …0%
Open Parking0%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

RMG Enterprises

PartnershipPromoter type
Raigarh, MAHARASHTRABased in
1Projects
1City
2026–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Sawantpur
Taluka
Palus
District
Sangli
Pincode
416308
Survey no.
Survey No 530, 534 to 541, Village: Sawantpur, Taluka: Palus, District:Sangli, 416308.
North boundary
CTS 542, 545 to 547 and 552
East boundary
CTS 554
South boundary
6 Meter Wide Road
West boundary
Boundary of Ramanand Nagar
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 2.2km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 2.9 km · Tasgaon RoadRailway line 526 mRailway station 808m away (Kirloskarvadi)Limited bus connectivity nearby
Water & environment
Canal 996 mRiver 4.5 km · Krishna
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra registration department

In Maharashtra it’s called the ready reckoner rate.

No government guidance rate is shown for this project.

Maharashtra's schedule is in Horizon's record, but this project's filed location couldn't be matched to one place with certainty — so no figure is shown rather than a guess.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

MahaRERA · Approved building plan

Town Planning And Valuation Department Sangli

Building Permit
Survey no. Survey No 530, 534 to 541, Village: Sawantpur, Taluka: Palus, District:Sangli, 416308.
The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

The planning authority

The body that approved this project. It has approved 4,607 RERA projects across 33 districts about 1 in 4 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

07

Other projects nearby

The register · within 25 km

18 residential projects still under way within 25 km. Step out ring by ring:

Of the 9 projects the radar draws within 6 km — every kind, every stage — 3 are residential projects still under way. This list keeps only those, and looks further out.

3 projects within 10 km — showing the nearest 3.

3.2 km awayOthers

NEW JADHAV COMPLEX

SHIVAJI SHANAKR JADHAV · Palus

Apr 2024registered
Jan 2027target completion
Government Guidance Rate₹21,539/sq ydScale42 flatsAuthorityMahaRERA
3.6 km awayResidential / Group Housing

SHIVTARA APARTMENT

SHIVRAJYA DEVELOPERS LLP · Palus

Oct 2025registered
Dec 2027target completion
Government Guidance Rate₹21,539/sq ydScale40 flatsAuthorityMahaRERA
4.0 km awayResidential / Group Housing

RAJ TOWERS

RAJ TOWERS · Palus

Jan 2025registered
Dec 2028target completion
no escrow declaredGovernment Guidance Rate₹21,539/sq ydScale42 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.