Complete project overview

MahaRERA · Registration filing
Units
1 units
Mix
1 × 4 BHK
Carpet area
224 sq mper-unit range, as filed
Floors
2
Parking
1 spaces
Land area
313 sq m
Sanctioned built-up
59,385 sq m
Recreational open space
6,065 sq m

Timeline

RERA registeredMar 2021
Proposed completionJun 2029
TodayJul 2026
Construction progress
Podiums0%
Stilt floor0%
Excavation100%
Basement (if any)100%
Plinth100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Internal Roads & F…100%
Water Supply100%
Sewerage (Chamber,…100%
Storm Water Drains100%
Landscaping & Tree…100%
Street Lighting100%
Community Building…100%
Treatment And Disp…100%
Water conservation…100%
Fire protection an…100%
Electrical meter r…100%
Aggregate area of …100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

1 units across 1 batch
TypeArea sq mCount
4 BHK2241

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

MahaRERA · Promoter registration

M/S Ganesh Ramchandra Apte

PartnershipPromoter type
Solapur, MAHARASHTRABased in
8Projects
1City
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
11 homeson the public record across 8 projects
2,57,933 sq mbuilt-up filed
10,646 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Solapur (M Corp.)
Taluka
Solapur North
District
Solapur
Pincode
413001
Survey no.
CST NO-8436,8437 F. P. NO-164/1/A
North boundary
OPEN SPACE
East boundary
7 METER WIDE ROAD
South boundary
PROPOSED ROW HOUSE NO-44
West boundary
PROPOSED ROW HOUSE NO-42
What’s nearby
SchoolsNearest school 2.0km away · College or university 1.8km away
HealthcareHospital 243m away · Clinic within 2km
LifestylePark 1.1km away
ShoppingNo supermarket within 2km
Getting around
Expressway 92 m · Degaon RoadPrimary road 789 m · Railway Station RoadRailway line 533 mRailway station 872m away (Solapur)Bus stop within 1km
Water & environment
Canal 2.8 km
distances only — not a flood assessment
Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.