HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
5
Buildings
2
Parking
26 spaces
Land area
1,393 sq m
Sanctioned built-up
1,520 sq m

Timeline

RERA registeredMay 2025
Proposed completionDec 2026
TodayJul 2026
Construction progress
Podiums0%
Stilt floor0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Community Building…0%
Treatment And Disp…0%
Solid Waste Manage…0%
Electrical meter r…0%
Superstructure32%
Plinth60%
Basement (if any)80%
Excavation100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

CHAKANKAR PROPERTIES

PartnershipPromoter type
Pune, MAHARASHTRABased in
1Projects
1City
2025–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Bavadhan BK
Taluka
Mulshi
District
Pune
Pincode
411021
Survey no.
SURVEY NO 100 P
North boundary
BY LAND BEARING S NO 100
East boundary
BY SKY I IRIS CO - OPEARTIVE HSG SOC LTD
South boundary
BY LAND BEARING S NO 100
West boundary
BY LAND BEARING S NO 100
What’s nearby
SchoolsNo schools within 2km · College or university 1.1km away · Library 1.2km away
HealthcareHospital 1.2km away · Clinic within 2km
LifestylePark 1.1km away · Gym or sports centre 996m away
ShoppingSupermarket 1.1km away
Getting around
Expressway 863 m · Katraj - Dehu Road BypassPrimary road 952 m · Paud RoadMetro station 4.7km away (Vanaz)Limited bus connectivity nearby
Water & environment
River 665 m · Ramnadi
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Pune Metropolitan Region Development Authority

Metropolitan Development Authority
Building Permit
Survey no. SURVEY NO 100 P
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Pune Metropolitan Region Development Authority

Metropolitan / development authority

Has approved 1,013 RERA projectsabout 1 in 20 in Maharashtra.

an apartments market87% apartments · 13% plotted layouts. Apartments like yours are this body's core business.

Builders
604
On record
21,940 flats · 10,299 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
EncumbranceDeclared financial encumbrance on the project
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.