HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
7
Buildings
2
Parking
14 spaces
Land area
414 sq m
Sanctioned built-up
777 sq m

Timeline

RERA registeredJul 2023
Proposed completionJun 2027
TodayJul 2026
Construction progress
Podiums0%
Storm Water Drains0%
OC-readiness90%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
Water Supply100%
Sewerage (Chamber,…100%
Water conservation…100%
Fire protection an…100%
Electrical meter r…100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

JYOTI SAGAR CORPORATION

PartnershipPromoter type
Mumbai Suburban, MAHARASHTRABased in
1Projects
1City
2023–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Bhandup
Taluka
Kurla
District
Mumbai Suburban
Pincode
400042
Survey no.
535/6
North boundary
PLOT NO 22
East boundary
PLOT NO 7
South boundary
MUNCIPAL ROAD
West boundary
INTERNAL ROAD
What’s nearby
SchoolsNearest school 1.5km away · College or university 1.3km away
HealthcareHospital 293m away · Clinic within 2km
LifestylePark 816m away · Gym or sports centre 1.9km away
ShoppingSupermarket 1.2km away · Mall 2.0km away · Convenience store within 500m
Getting around
Expressway 630 m · Eastern Express HighwayPrimary road 624 m · Goregaon - Mulund Link RoadRailway line 379 m · Central Railways Slow LineRailway station 469m away (Nahur)Bus stop within 500m
Water & environment
Water body 370 mRiver 2.0 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Municipal Corporation of Greater Mumbai

Municipal Corporation · MCGM
Building Permit
Survey no. 535/6
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation of Greater Mumbai

Municipal corporation

Has approved 2,862 RERA projectsabout 1 in 7 in Maharashtra, more than any other body in the state.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
2,166
On record
34,498 flats · 0 plots
Reach
9 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.