Complete project overview

RAJ-RERA · Registration filing
Units
60 units
Mix
7 × LIG-06 · 7 × LIG-08 · 7 × EWS-01 · 7 × LIG-07 · 7 × LIG-05 · 7 × EWS-02
Carpet area
7–34 sq mper-type range, as filed
Land area
1,251 sq m
Completion deadline extended
1 extension on record — latest to 31 Dec 2023declared reason: force majeure

Timeline

Construction startAug 2019
RERA registeredOct 2019
Proposed completionDec 2022
TodayJul 2026

Find your unit

Filed by type and size, in the batches the promoter registered — not a per-unit listing. Look yours up.

60 units across 12 batches
BuildingTypeArea sq mCount
JAGDISH HOMES IILIG-06347
JAGDISH HOMES IILIG-08347
JAGDISH HOMES IIEWS-01227
JAGDISH HOMES IILIG-07347
JAGDISH HOMES IILIG-05347
JAGDISH HOMES IIEWS-02207
JAGDISH HOMES IILIG-04347
JAGDISH HOMES IILIG-03347
JAGDISH HOMES IIShop-04121
JAGDISH HOMES IIShop-0291
JAGDISH HOMES IIShop-03101
JAGDISH HOMES IIShop-0171

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

RAJ-RERA · Promoter registration

MOJIKA REAL ESTATE AND DEVELOPERS PVT LTD

OrganisationPromoter type
Jaipur, RajasthanBased in
10Projects
2Cities
2017–2023Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
840 homeson the public record across 10 projects
1,37,175 sq mbuilt-up filed
66,050 sq mland declared
₹330.15 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
5, HANUMAN VATIKA, A-7, Saligrampura, Sanganer, Jaipur, 303905
Village
Saligrampura
Taluka
Sanganer
District
Jaipur
Pincode
303905
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 4.6km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 4.8 km · Tonk Road FlyoverRailway line 3.7 kmNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
Water body 1.1 km · Dravyavati RiverRiver 4.2 km · Dhund
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹2.87 Cr declared to build 60 flats. What that works out to:

₹4.79 Lakhdeclared cost per flatall-in — land + construction
₹914/sq ftof built-up area₹9,840/sq m
23%of the cost is land₹501/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan
Building Permitapproved 25 Oct 2019 · 6 yrs ago

The promised possession date (31 Dec 2022) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.