Complete project overview

RAJ-RERA · Registration filing
Land area
11,245 sq m
Completion deadline extended
2 extensions on record — latest to 30 Jan 2022declared reason: force majeure
Description
The Project MOJIKA HOMES which is proposed under chief minister jan awas yojana. This project is approved by empanelled architect, as per UDH letter dated 31.05.2017, Shri Ankur Singh Tanwar, COA No. CA/2011/51904, Address: Skyline Planners and Design Developers, 31, Shiv Path, Suraj Nagar (West), Civil Line, Jaipur-302006.The Estimated Finish date of the project was extended on 06-02-2021. This bears the approval of Honorable Chairman, before extension the estimated finish date was 30-01-2020.

Timeline

RERA registeredJan 2018
Construction startMar 2018
Proposed completionJan 2021
TodayJul 2026
02

Builder’s track record

RAJ-RERA · Promoter registration

MOJIKA REAL ESTATE AND DEVELOPERS PVT LTD

OrganisationPromoter type
Sikar, RajasthanBased in
10Projects
2Cities
2017–2023Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
840 homeson the public record across 10 projects
1,37,175 sq mbuilt-up filed
66,050 sq mland declared
₹330.15 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
1191/238, 1190/238 , NEAR JAIPUR JHUNJHUNU BYPASS, GHORANA, KUDLI, PIPRALI, Sikar, 302024
Village
GHORANA, KUDLI
Taluka
PIPRALI
District
Sikar
Pincode
302024
What’s nearby
SchoolsNearest school 1.2km away · College or university 1.7km away · Library 885m away
HealthcareHospital 1.2km away · Clinic within 2km
LifestylePark 1.2km away · Gym or sports centre 1.2km away
ShoppingSupermarket 1.1km away · Mall 1.3km away · Convenience store within 1km
Getting around
Primary road 354 mRailway line 2.4 kmRailway station 3.1km away (Sikar Railway Station)Limited bus connectivity nearby
Price analysisdeclared build cost — not a sale price

₹29.28 Cr declared. What that works out to:

3%of the cost is land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan
Building Permitapproved 19 Jan 2018 · 8 yrs ago

The promised possession date (30 Jan 2021) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.