Complete project overview

MahaRERA · Registration filing
Floors
8
Buildings
2
Parking
39 spaces
Land area
1,094 sq m
Sanctioned built-up
17,85,026 sq m

Timeline

RERA registeredNov 2021
Proposed completionMay 2025
TodayJul 2026
Construction progress
Energy managemcnt0%
Fire protection an…0%
Excavation100%
Basement (if any)100%
Podiums100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Internal Roads & F…100%
Water Supply100%
Sewerage (Chamber,…100%
Storm Water Drains100%
Landscaping & Tree…100%
Street Lighting100%
Treatment And Disp…100%
Solid Waste Manage…100%
Water conservation…100%
Electrical meter r…100%
Open Parking100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

PANCHRATNA DEVELOPERS

PartnershipPromoter type
Satara, MAHARASHTRABased in
6Projects
6Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
213 homeson the public record across 6 projects
18,00,516 sq mbuilt-up filed
12,157 sq mland declared
₹4.98 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Ahmedabad Urban Development AuthorityUrban Development Authority1 of 3 projects
Kalyan Dombivli Municipal CorporationMunicipal Corporation1 of 3 projects
Vaduj Nagar PanchayatMunicipal Councilthis project1 of 3 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Vaduj
Taluka
Khatav
District
Satara
Pincode
415506
Survey no.
GAT NO 71/2/1/1/1/2
North boundary
9 Mtr Wide Road
East boundary
Open Space
South boundary
gat no 76
West boundary
18 Mtr wide Road
What’s nearby
Schools1 school within 500m · College or university 173m away
HealthcareHospital 81m away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Primary road 57 m · Vaduj Karad RoadNo metro or railway within 5km3 bus stops within 500m
Water & environment
River 243 m · Yerala RiverWater body 578 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Vaduj Nagar Panchayat

Municipal Council
Building Permit
Survey no. GAT NO 71/2/1/1/1/2

The promised possession date (31 May 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation

A city municipal corporation that sanctions projects within its own limits. It has approved 12,653 RERA projects across 34 districts about 1 in 2 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.