Complete project overview

MahaRERA · Registration filing
Buildings
2
Parking
221 spaces
Land area
1,924 sq m

Timeline

RERA registeredOct 2025
Proposed completionMar 2029
TodayJul 2026
Construction progress
Basement (if any)0%
Podiums0%
Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Community Building…0%
Water conservation…0%
Fire protection an…0%
Electrical meter r…0%
Plinth80%
Excavation100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

TRINITY CREATIVE HOMES LLP

Limited Liability PartnershipPromoter type
Thane, MAHARASHTRABased in
2Projects
2Cities
2024–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
2 projectson the public record across 2 projects
22,972 sq mbuilt-up filed
5,578 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Municipal Corporation of Greater MumbaiMunicipal Corporationthis project1 of 2 projects
Thane Municipal CorporationMunicipal Corporation1 of 2 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Mulund
Taluka
Kurla
District
Mumbai Suburban
Pincode
400081
Survey no.
CTS.NO.1320/B-1
North boundary
By Aaditya darshan CHS Ltd
East boundary
By public Housing Reserve Plot.
South boundary
By Nalla and Creek
West boundary
By 1320/B-9 & Surya Darshan CHS Ltd
What’s nearby
Schools3 schools within 500m · 6 educational institutions within 1km · College or university 1.2km away
HealthcareHospital 414m away · 5 clinics within 1km · Pharmacy within 500m
LifestylePark 1.6km away · Gym or sports centre 653m away · 40+ restaurants and cafes within 1km
ShoppingSupermarket 666m away · Convenience store within 1km · Bank 145m away
Getting around
Expressway 233 m · Eastern Express HighwayPrimary road 1.8 km · Lal Bahadur Shastri MargRailway line 771 m · Central Railways Slow LineRailway station 917m away (Mulund)4 bus stops within 500m
Water & environment
Water body 494 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Municipal Corporation of Greater Mumbai

Municipal Corporation
Building Permit
Survey no. CTS.NO.1320/B-1
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation of Greater Mumbai

Municipal corporation

Has approved 2,862 RERA projectsabout 1 in 7 in Maharashtra, more than any other body in the state.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
2,166
On record
34,498 flats · 0 plots
Reach
9 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

1 complaint on MahaRERA’s register for this project 1 disposed.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.