HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
7
Buildings
2
Parking
25 spaces
Land area
2,544 sq m
Sanctioned built-up
3,235 sq m

Timeline

RERA registeredAug 2017
Proposed completionAug 2023
TodayJul 2026
Construction progress
Podiums0%
Stilt floor0%
Flat fit-out0%
External finishes0%
OC-readiness0%
Internal Roads & F…0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Street Lighting0%
Treatment And Disp…0%
Water conservation…0%
Energy managemcnt0%
Fire protection an…0%
Electrical meter r…0%
Aggregate area of …0%
Internal finishes20%
Water Supply40%
Stairs & lifts50%
Superstructure86%
Excavation100%
Basement (if any)100%
Plinth100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Jitendra Constructions

PartnershipPromoter type
Pune, MAHARASHTRABased in
1Projects
1City
2017–2023Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Pashan
Taluka
Haveli
District
Pune
Pincode
411045
Survey no.
Survey No 5/4A, 4B, 5, 5/7
North boundary
By S no 5 1 and 5 2 and beyond that gaothan
East boundary
By Land Of T R Nihman
South boundary
By S No 6 Sutarwadi Pashan
West boundary
BY P M C Road
What’s nearby
Schools1 school within 500m
HealthcareHospital 126m away · 3 clinics within 1km
LifestyleNo parks within 2km · 3 restaurants and cafes within 1km
ShoppingNo supermarket within 2km
Getting around
Primary road 102 m · Bassein RoadRailway line 1.4 km · Western Railway Virar to BorivaliRailway station 1.5km away (Vasai Road)Limited bus connectivity nearby
Water & environment
Water body 430 mRiver 2.0 km
distances only — not a flood assessment
Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.