HORIZONMarkets
01

Complete project overview

RAJ-RERA · Registration filing
Units
48 units
Mix
24 × 2 BHK · 24 × 3 BHK
Carpet area
62–96 sq mper-type range, as filed
Land area
1,212 sq m

Timeline

Construction startNov 2021
RERA registeredNov 2021
Proposed completionDec 2024
TodayJul 2026

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

48 units across 8 batches
BuildingTypeArea sq mCount
JVJ ANTILLIA2 BHK626
JVJ ANTILLIA3 BHK956
JVJ ANTILLIA3 BHK966
JVJ ANTILLIA3 BHK936
JVJ ANTILLIA2 BHK626
JVJ ANTILLIA2 BHK626
JVJ ANTILLIA3 BHK866
JVJ ANTILLIA2 BHK636

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

RAJ-RERA · Promoter registration

JVJ DREAM DEVELOPERS LLP

OrganisationPromoter type
Jaipur, RajasthanBased in
4Projects
1City
2020–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
192 homeson the public record across 4 projects
32,232 sq mbuilt-up filed
5,980 sq mland declared
₹79.69 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
1,2,9,10 & 11, Gulab Vihar Scheme, Gram Narsinghpura, Sanganer, Jaipur, 302026
Village
Gram Narsinghpura
Taluka
Sanganer
District
Jaipur
Pincode
302026
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 3.1km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 908 m · Jaipur Kishangarh ExpresswayNo metro or railway within 5kmBus stop within 1km
Price analysisdeclared build cost — not a sale price

₹10.75 Cr declared to build 48 flats. What that works out to:

₹22.40 Lakhdeclared cost per flatall-in — land + construction
₹1,714/sq ftof built-up area₹18,452/sq m
16%of the cost is land₹1,342/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan

Jaipur Development Authority

Development Authority
Building Permitapproved 27 Nov 2021 · 4 yrs ago

The promised possession date (31 Dec 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Jaipur Development Authority

Development authority

Has approved 644 RERA projectsabout 1 in 3 in Rajasthan, more than any other body in the state.

a mixed market52% apartments · 48% plotted layouts.

Builders
528
On record
15,937 flats · 30,970 plots
Reach
2 districts
Since
2017

More apartment-heavy than Rajasthan overall — 52% apartments here vs 34% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.