01

Complete project overview

RAJ-RERA · Registration filing
Project name
JVJ DREAM RESIDENCY
Land area
967 sq m

Timeline

Construction startJan 2020
RERA registeredMay 2020
Proposed completionDec 2021
TodaySep 2026
02

Builder’s track record

RAJ-RERA · Builder registration

JVJ DREAM DEVELOPERS LLP

OrganisationPromoter type
Jaipur, RajasthanBased in
4Projects
1City
2020–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
192 homeson the public record across 4 projects
32,232 sq mbuilt-up filed
5,980 sq mland declared
₹79.69 Crdeclared build cost

Build cost is what the builder declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from JVJ DREAM DEVELOPERS LLP— the full portfolio →

03

Location & price analysis

RAJ-RERA · Registration filing
Address
65,66,81,82, SCHEME PREM SAGAR, NARSINGHPURA, Jaipur, Jaipur, 302020
Village
NARSINGHPURA
Taluka
Jaipur
District
Jaipur
Pincode
302020
What’s nearby
Schools1 school within 1km
HealthcareHospital 170m away · 2 clinics within 1km
LifestylePark 1.5km away · Swimming pool within 2km
ShoppingNo supermarket within 2km · Bank 935m away
Getting around
Expressway 385 mPrimary road 1.3 kmRailway line 3.1 kmMetro station 1.4km away (Manasarovar)Limited bus connectivity nearby
Water & environment
Water body 1.2 km · Dravyavati River
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹5.95 Cr declared. What that works out to:

16%of the cost is land

This is what the builder filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Government Guidance Rate

Rajasthan IGRS — DLC rates (rural branch)

In Rajasthan it’s called the DLC rate.

₹1,087per sq yd
₹1,300per sq m
Which rate
residential, interior plot
Matched to
The rate published for the village of “NARSINGH PURA”.

What this number is — and isn’t

  • The minimum value Rajasthan’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
  • Not a market price. Sales normally register above it, and how far above varies by place and by project.
  • Its fit depends on the grain the state publishes at. This one is matched at the level of village, and says so above. How Horizon decides what to show.
05

Planning authority

RAJ-RERA · Approved building plan

Jaipur Development Authority

Development Authority
Building Permitapproved 29 May 2020 · 6 yrs ago

The promised possession date (31 Dec 2021) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Jaipur Development Authority

Development authority

Has approved 644 RERA projectsabout 1 in 3 in Rajasthan, more than any other body in the state.

a mixed market52% apartments · 48% plotted layouts.

Builders
528
On record
15,937 flats · 30,970 plots
Reach
2 districts
Since
2017

More apartment-heavy than Rajasthan overall — 52% apartments here vs 34% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by RAJ-RERA

07

Other projects nearby

The register · within 25 km

421 residential projects still under way within 25 km. Step out ring by ring:

Of the 565 projects the radar draws within 6 km — every kind, every stage — 160 are residential projects still under way. This list keeps only those, and looks further out.

7 projects within 1 km — showing the nearest 6.

300 m awayGroup Housing

SPACE VILLAS

One Realty Group · Sanganer · Jaipur

Jul 2023registered
Mar 2026target completion
possession revisedDeclared cost₹27.00 CrScale67 flatsAuthorityRAJ-RERA
390 m awayGroup Housing

Gulmohar Apartment

RAJASTHAN HOUSING BOARD · Sanganer · Jaipur

Apr 2025registered
Dec 2030target completion
Declared cost₹121.77 CrScale168 flatsAuthorityRAJ-RERA
510 m awayGroup Housing

THE ROYAL PALACE

SHREE RAM INFRA · Jaipur

Mar 2025registered
Jun 2027target completion
Declared cost₹15.55 CrScale48 flatsAuthorityRAJ-RERA
630 m awayGroup Housing

AG HEIGHTS III

Aaradhya Govind Developers · Sanganer · Jaipur

Apr 2025registered
Mar 2026target completion
Declared cost₹8.83 CrScale24 flatsAuthorityRAJ-RERA
790 m awayGroup Housing

The Urban Crest

Shree Gurukripa Homes · Jaipur

May 2025registered
Dec 2028target completion
Declared cost₹10.50 CrScale48 flatsAuthorityRAJ-RERA
910 m awayGroup Housing

The Twin Tower

Shree Salasar Developers · Jaipur

Jun 2025registered
Dec 2029target completion
Declared cost₹11.80 CrScale30 flatsAuthorityRAJ-RERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.