Complete project overview

WBRERA · Registration filing
Apartments
13
Commercial units
1
Land area
342 sq m
Built-up area
753 sq m
Carpet area
553 sq m
Parking
4 spaces
RERA registered
2024

Timeline

RERA registeredJan 2024
Proposed completionJun 2025
Revised completionJun 2026
TodayJul 2026
02

Builder’s track record

WBRERA · Promoter registration

S.S. CONSTRUCTION

Proprietorship FirmPromoter type
Kolkata, West BengalBased in
4Projects
3Cities
2024–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
38 homeson the public record across 4 projects
2,385 sq mbuilt-up filed
1,938 sq mland declared
₹2.53 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Kolkata Municipal CorporationMunicipal Corporationthis project2 of 4 projects
Asansol Municipal CorporationMunicipal Corporation1 of 4 projects
Guwahati Municipal CorporationMunicipal Corporation1 of 4 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

WBRERA · Registration filing
District
Kolkata
Police station
Bansdroni
Address
Premises No. 45 Rifle Club Road, Ward No. 113
Pincode
700070
What’s nearby
Schools2 schools within 500m · College or university 1.5km away
HealthcareHospital 1.4km away · 1 clinic within 1km · Pharmacy within 1km
LifestylePark 1.7km away · Gym or sports centre 1.8km away
ShoppingSupermarket 1.0km away
Getting around
Expressway 4.4 km · Diamond Harbour RoadPrimary road 1.0 km · Netaji Subhash Chandra Bose RoadRailway line 3.6 kmMetro station 1.5km away (Netaji)Limited bus connectivity nearby
Water & environment
Water body 362 mRiver 803 m · Adi Ganga
distances only — not a flood assessment
04

Planning authority

WBRERA · Approved building plan

Kolkata Municipal Corporation

Municipal Corporation
Building Permit

The promised possession date (30 Jun 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Kolkata Municipal Corporation

Municipal corporation / municipality

Has approved 1,030 RERA projectsabout 1 in 2 in West Bengal, more than any other body in the state.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
776
On record
14,568 flats · 0 plots
Reach
5 districts

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Compliance & litigation record
Defaulter listThis developer appears on WBRERA's defaulter list
WBRERA lists the developers it has flagged as defaulters — that line is the authority's own record; any litigation line is the promoter's own declaration at registration. A flagged line is worth verifying directly with WBRERA; none of it is a verdict on the project.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — WBRERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — WBRERA does not publish a complaints register. This read cannot speak to them either way.
  • Escrow — WBRERA does not publish escrow declarations. Whether buyer money is ring-fenced cannot be read here.