Complete project overview

MahaRERA · Registration filing
Units
140 units
Mix
76 × 3 BHK · 32 × 2 BHK · 24 × Shop · 8 × 1 BHK
Carpet area
26–88 sq mper-unit range, as filed
Floors
16
Buildings
2
Parking
116 spaces
Land area
1,962 sq m
Sanctioned built-up
12,810 sq m
Recreational open space
2,421 sq m

Timeline

RERA registeredFeb 2023
Proposed completionDec 2026
TodayJul 2026
Construction progress
Water Supply0%
Landscaping & Tree…0%
Street Lighting0%
Water conservation…0%
Electrical meter r…0%
Aggregate area of …0%
Internal Roads & F…50%
Energy managemcnt50%
Fire protection an…50%
OC-readiness75%
Flat fit-out90%
Excavation100%
Basement (if any)100%
Podiums100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Stairs & lifts100%
External finishes100%
Sewerage (Chamber,…100%
Storm Water Drains100%
Community Building…100%
Treatment And Disp…100%
Solid Waste Manage…100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

140 units across 15 batches
TypeArea sq mCount
2 BHK532
1 BHK482
1 BHK452
1 BHK502
1 BHK512
2 BHK532
2 BHK6626
3 BHK7624
2 BHK542
3 BHK8824
3 BHK8826
3 BHK702
Shop811
Shop261
Shop2722

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

MahaRERA · Promoter registration

Unique Chintamani Development LLP

PartnershipPromoter type
Pune, MAHARASHTRABased in
4Projects
1City
2019–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
558 homeson the public record across 4 projects
72,921 sq mbuilt-up filed
15,684 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Pimpri Chinchawad (M Corp.)
Taluka
Haveli
District
Pune
Pincode
412101
Survey no.
Sr. No. 67/1, Kiwale
North boundary
By Building B
East boundary
By 9 Mtr Wide Road
South boundary
By 45 Mtr Wide Road
West boundary
By Part of S No 67
What’s nearby
SchoolsNearest school 1.9km away
HealthcareHospital 517m away · 1 clinic within 1km · Doctor's clinic within 1km
Lifestyle1 park within 500m · 27+ restaurants and cafes within 1km
ShoppingSupermarket 144m away · Convenience store within 500m · Bank 901m away
Getting around
Expressway 120 m · Gramdaivat Shree Bapdev Maharaj FlyoverPrimary road 28 mRailway line 1.4 km · Mumbai–Pune RailwayRailway station 2.2km away (Dehu Road)Bus stop within 1km
Water & environment
Water body 1.6 km
distances only — not a flood assessment
Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.