Complete project overview

RERA Telangana · Registration filing
Units
10 units
Unit mix
10 × 3BHK
Saleable area
133 sq mper unit, as filed
Floors
5
Land area
477 sq m
Built-up area
1,386 sq m

Timeline

RERA approvedAug 2021
Proposed completionAug 2024
TodayJul 2026
Construction progress

40% overall, as filed

Basement & plinth0%
Podiums0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Excavation100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

10 of 10 available
BuildingFloorTypeArea sq mAvailable
KAKATIYA DIAMOND HEIGHTS-113BHK1332 of 2
KAKATIYA DIAMOND HEIGHTS-123BHKmortgaged1332 of 2
KAKATIYA DIAMOND HEIGHTS-133BHK1332 of 2
KAKATIYA DIAMOND HEIGHTS-143BHK1332 of 2
KAKATIYA DIAMOND HEIGHTS-153BHK1332 of 2

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

KAKATIYA INFRA PROJECTS

PartnershipPromoter type
Hyderabad, TelanganaBased in
4Projects
2Cities
2018–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
65 homeson the public record across 4 projects
8,731 sq mbuilt-up filed
6,067 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Telangana · Registration filing
Locality
NAGARAM
Village
Rampally
Mandal
Keesara
District
Medchal-Malkajgiri
Pincode
500062
North boundary
OPEN PLOT
East boundary
OPEN PLOT
South boundary
OPEN PLOT
West boundary
60FT WIDE ROAD
What’s nearby
SchoolsNearest school 1.2km away
HealthcareHospital 965m away · Pharmacy within 1km
LifestyleNo parks within 2km · Gym or sports centre 900m away
ShoppingSupermarket 1.1km away · Mall 945m away
Getting around
Primary road 876 m · ECIL-Keesara RoadRailway line 3.2 kmRailway station 3.4km away (Charlapalli)Bus stop within 1km
Declared external development
Roads0%
Water supply0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
Price analysisno declared cost on this filing — one government benchmark below

This state’s RERA filing carries no declared build cost at all — nothing to turn into a per-unit or per-sq-ft figure here. The one real, government-sourced number below is the closest thing to a benchmark this record can offer.

Government guidance value
₹3,500/sq ydresidential

₹4,186/sq m · effective May 2026 · apartments ₹2,700/sq ft, same source

The state’s minimum value for this locality’s land, set for stamp duty — a floor, not a market price. Source: Telangana Registration & Stamps.

04

Planning authority

RERA Telangana · Approved building plan

Hyderabad Metropolitan Development Authority (HMDA)

Urban Development Authority
Building Permit
Survey no. 67P, 68P, 69P AND 714P

The promised possession date (11 Aug 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

HMDA

Urban Development Authority · Hyderabad metropolitan periphery

Has approved 3,643 RERA projectsabout 1 in 3 in Telangana.

an apartments market72% apartments · 28% plotted layouts. Apartments like yours are this body's core business.

Builders
2,462
On record
3,98,695 flats · 1,96,015 plots
Reach
71 mandals
Since
2016

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.