HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
19
Buildings
2
Parking
15 spaces
Land area
778 sq m
Sanctioned built-up
551 sq m
Recreational open space
778 sq m

Timeline

RERA registeredApr 2018
Proposed completionJun 2021
TodayJul 2026
02

Builder’s track record

MahaRERA · Promoter registration

IKIRA BUILD TECH LLP

PartnershipPromoter type
Mumbai Suburban, MAHARASHTRABased in
1Projects
1City
2018–2021Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Borivali
Taluka
Borivali
District
Mumbai Suburban
Pincode
400067
Survey no.
154,154
North boundary
PANCHAM APARTMENT
East boundary
KAILASH DARSHAN APARTMENT
South boundary
HEMUKALANI ROAD NO 3
West boundary
SAIRAJ GARDEN CHS LTD
What’s nearby
Schools1 school within 500m · 4 educational institutions within 1km · College or university 588m away
HealthcareHospital 416m away · 12 clinics within 1km · Pharmacy within 1km
Lifestyle2 parks within 500m · Gym or sports centre 1.0km away · 14+ restaurants and cafes within 1km
ShoppingSupermarket 1.3km away · Mall 775m away · Convenience store within 1km
Getting around
Expressway 2.2 kmPrimary road 675 m · Link RoadRailway line 1.1 km · Western Railway Virar to BorivaliMetro station 765m away (Dahanukarwadi)2 bus stops within 500m
Water & environment
Water body 476 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Municipal Corporation of Greater Mumbai

Municipal Corporation
Building Permit
Survey no. 154,154

The promised possession date (30 Jun 2021) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation of Greater Mumbai

Municipal corporation

Has approved 2,862 RERA projectsabout 1 in 7 in Maharashtra, more than any other body in the state.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
2,166
On record
34,498 flats · 0 plots
Reach
9 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.