HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
4
Buildings
5
Parking
32 spaces
Land area
2,972 sq m
Sanctioned built-up
2,900 sq m
Recreational open space
72 sq m

Timeline

RERA registeredOct 2020
Proposed completionJun 2025
TodayJul 2026
Construction progress
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Landscaping & Tree…0%
Solid Waste Manage…0%
Water conservation…0%
Fire protection an…0%
Electrical meter r…0%
Excavation100%
Basement (if any)100%
Podiums100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

KANDRE DEVELOPER

PartnershipPromoter type
Solapur, MAHARASHTRABased in
3Projects
1City
2020–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
3 projectson the public record across 3 projects
6,916 sq mbuilt-up filed
7,058 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Pandharpur Municipal CouncilMunicipal Councilthis project2 of 3 projects
Municipal Council PandharpurMunicipal Council1 of 3 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Isbavi
Taluka
Pandharpur
District
Solapur
Pincode
413304
Survey no.
25/1 and 2 and 26/2
North boundary
11MTR road
East boundary
11MTR
South boundary
12MTR Road
West boundary
12MTR
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 816m away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 179 mPrimary road 1.9 kmRailway line 2.1 kmRailway station 2.2km away (Pandharpur)Limited bus connectivity nearby
Water & environment
River 2.4 km · BhimaCanal 2.5 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Pandharpur Municipal Council

Municipal Council
Building Permit
Survey no. 25/1 and 2 and 26/2

The promised possession date (30 Jun 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Pandharpur Municipal Council

Municipal corporation

Has approved 7 RERA projects0% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
6
On record
97 flats · 0 plots
Since
2020

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.