Complete project overview

MahaRERA · Registration filing
Floors
5
Buildings
6
Parking
117 spaces
Land area
5,980 sq m
Sanctioned built-up
5,524 sq m

Timeline

RERA registeredJan 2023
Proposed completionJun 2027
TodayJul 2026
Construction progress
Basement (if any)0%
Podiums0%
Flat fit-out0%
Water Supply0%
Sewerage (Chamber,…0%
Landscaping & Tree…0%
Electrical meter r…0%
OC-readiness8%
Internal finishes50%
Stilt floor60%
External finishes68%
Stairs & lifts81%
Excavation100%
Plinth100%
Superstructure100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Sunil Chamanlal Gupta

IndividualPromoter type
Thane, MAHARASHTRABased in
3Projects
1City
2018–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
69 homeson the public record across 3 projects
7,654 sq mbuilt-up filed
8,018 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Cheravali
Taluka
Panvel
District
Raigarh
Pincode
410206
Survey no.
Survey No 3/1/A
North boundary
Survey No 57
East boundary
Survey No 3 Hissa 1B
South boundary
Survey No 3 Hissa No 1B
West boundary
Survey No 56
What’s nearby
SchoolsNo schools within 2km
HealthcareNo hospital within 5km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Primary road 1.1 km · SH 54No metro or railway within 5kmLimited bus connectivity nearby
Water & environment
River 158 mWater body 484 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Navi Mumbai Airport Influence Notified Area

Building Permit
Survey no. Survey No 3/1/A
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Navi Mumbai Airport Influence Notified Area

Planning authority

Has approved 16 RERA projects0.1% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
12
On record
0 flats · 0 plots
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.