Complete project overview

MahaRERA · Registration filing
Floors
12
Buildings
2
Parking
24 spaces
Land area
6,800 sq m
Sanctioned built-up
5,900 sq m
Recreational open space
500 sq m

Timeline

RERA registeredAug 2019
Proposed completionDec 2024
TodayJul 2026
Construction progress
Podiums0%
Stilt floor0%
Flat fit-out10%
OC-readiness25%
Water Supply50%
Landscaping & Tree…50%
Street Lighting50%
Water conservation…50%
Energy managemcnt50%
Fire protection an…50%
Electrical meter r…50%
Sewerage (Chamber,…60%
Storm Water Drains60%
Internal finishes80%
Stairs & lifts88%
External finishes90%
Treatment And Disp…90%
Excavation100%
Basement (if any)100%
Plinth100%
Superstructure100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

ARIHANT PROPERTIES

PartnershipPromoter type
Pune, MAHARASHTRABased in
1Projects
1City
2019–2024Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
CHARHOLI
Taluka
Haveli
District
Pune
Pincode
412105
Survey no.
SURVEY NO-149/14,14/13/1,149/13/2
North boundary
SURVEY NO-149-12
East boundary
HISSA NO-10
South boundary
SURVEY NO-149-15
West boundary
PUNE ALANDI ROAD
What’s nearby
Schools1 school within 1km · College or university 828m away
HealthcareHospital 466m away · Clinic within 2km
LifestylePark 591m away · 7 restaurants and cafes within 1km · Swimming pool within 2km
ShoppingSupermarket 621m away · Bank 622m away
Getting around
Expressway 53 m · Pune Nashik RoadPrimary road 1.0 km · Spine RoadRailway line 4.6 km · Mumbai–Pune RailwayMetro station 4.5km away (Sant Tukaram Nagar)Bus stop within 1km
Water & environment
Water body 1.5 km · PCMC Water Tank
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Pimpri Chinchwad Municipal Corporation

Municipal Corporation
Building Permit
Survey no. SURVEY NO-149/14,14/13/1,149/13/2

The promised possession date (30 Dec 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Pimpri Chinchwad Municipal Corporation

Municipal corporation

Has approved 1,391 RERA projectsabout 1 in 14 in Maharashtra.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,080
On record
9,009 flats · 249 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.